ANNEX
ANNEX REFERRED TO IN REPLY TO
PARTs (a) TO (c) OF UNSTARRED QUESTION NO. 2910 TO BE ANSWERED IN THE RAJYA SABHA ON 29.08.2011.
**********
1. De-licensing
of power generation
Generation has been
delicensed and captive generation is permitted. Hydro projects would, however, need approval of the State
Government and concurrence from the Central Electricity Authority for a scheme
estimated to involve a capital expenditure exceeding such sum as may be fixed
by the Central Government, from time to time, by notification.
Electricity generation in the country from the conventional sources and import of energy from Hydro Power Stations located in Bhutan increased from approximately 530 Billion Unit (BU) in 2003-04 to 771.5 BU in 2009-10.
2. Competition in power generation
Guidelines for competitive bidding for procurement of Power by distribution licensees under the Electricity Act have been issued on 19.1.2005 by the Central Government. Based on these guidelines, large coal based Ultra Mega Power Projects of 4000MW each are being developed though private sector participation. UMPPs will use more efficient super critical technology for generation of power. Tariff based International Competitive Bidding has been followed for selection of project developer. Four UMPP projects have been awarded – two pit head based viz. Sasan UMPP (6x660 MW) in Madhya Pradesh &Tilaiya UMPP (6x660 MW) to M/s Reliance Power Limited in Jharkhand and two coastal viz. Mundra UMPP (5x800 MW) in Gujarat &Krishnapatnam UMPP (5x800 MW) in Andhra Pradesh to M/s Tata Power Company and M/s Reliance Power Limited respectively.
The States are also actively involved in
procurement of power through tariff based competitive bidding under Case-I
based on the above guidelines.
3. Liberal
provisions for captive power generation:
Captive generation has been liberalised in
order to promote investment. Captive power generation has benefitted immensely
from this and has reached 19,509MW as on 31.03.2010 as per the information of
Central Electricity Authority. A number of captive power plants have been
selling surplus power through the power exchanges. Thus, a lot of latent
capacity has come into the market. These are positive developments leading to
an increase in the availability of power and the consequent depth of the power
market.
4. Mandatory
setting up of Regulatory Commissions and formulation of their role and
functions:
Electricity Regulatory Commissions have been established in most States and Union Territories to regulate the sector including award and revoking of licences, tariff setting consistent with National Electricity Policy and Tariff Policy defining and enforcing performance standards and quality of service to consumers.
5. Unbundling of State Electricity Boards (SEBs)
Under Section 131 of Electricity Act 2003, it has been mandated to
reorganize the State Electricity Boards in the country to separate entities of
Generation, Transmission and Distribution segments with the purpose of making
them self sustaining. As on date 18 numbers of SEBs have been reorganized. This has helped in more accurate accounting
of different businesses in power sector and brought about a commercial
orientation among the unbundled utilities.
6. Open
Access to Transmission /Distribution Systems
The Open Access at inter-state level is fully
operational. With regard to Open Access at Inter-State level, during the
financial year 2009 - 10, the total number of transactions under Open Access
was 18128 as against 778 in 2004-05. As per information available with
Forum of Regulators Secretariat, 24 SERCs have notified terms and conditions of
Open Access Regulations, 20 SERCs have determined cross subsidy surcharge, 25
SERCs have allowed Open Access up to 1 MW
and above, 22 SERCs have determined transmission charges and 18 SERCs
have determined wheeling charges.
7. Power Trading recognized as a licensed activity
Power Trading has been
recognized as a licensed activity, apart from generation, transmission and
distribution and the Appropriate Regulatory Commissions have been empowered to
fix the trading margins, if considered necessary. About 40 inter-state trading licensees are there and the volume
of traded electricity in 2009-10 was 33.91 BUs as against only 11.85 BUs in
2004-05. CERC has given approval to power exchange based transactions involving
sale and purchase of electricity. Indian Energy Exchange and Power Exchange of
India Limited are the two operational power exchanges in the country.
Electricity trade through bilateral trading constitutes about 4 % of traded
power and about 1 % is traded through power exchanges.
8. Regulatory
Commissions to develop electricity markets
The Central Commission has issued power
market regulations. With this, the market structure in the electricity sector
has been codified. The regulations have defined various types of contracts and
the roles and responsibilities of various market players. Through new trading
margin regulations, long-term agreements have been exempted from trading margin
in order to facilitate innovative products and contracts for new capacity
addition which involves higher risk in transaction. Provisions have also been
made to ensure that traders do not circumvent the ceiling of trading margin by
routing the electricity through multiple transactions.
9. Establishment
of Appellate Tribunal
An Appellate Tribunal has been established for disposal of appeals against the decision of the CERC and State Electricity Regulatory Commissions so that there is speedy disposal of such matters.
10. Constitution
of Forum of Regulators
The Forum of Regulator was constituted vide
Notification in February 2005 in pursuance of the provisions under Section 166
(2) of the Electricity Act, 2003. to provide a common platform to Regulatory
commissions across the nation for deliberation on Regulatory issues in order to
harmonize regulatory practices in the best possible manner.
11. Safeguarding
consumer interests
Specific provisions have been made in The
Electricity Act, 2003 relating to consumer protection. The Consumer Grievances
Redressalfora have been constituted in 29 States and in 25 States, Ombudsman
has been appointed.
12. Restructured-Accelerated
Power Development and Reforms Programme (R-APDRP)
For the reduction of AT&C losses on sustainable basis and improvement in power distribution sector, Government of India has launched Restructured-Accelerated Power Development and Reforms Programme (R-APDRP) during 11th Plan period as a central sector scheme.The focus of R-APDRP Scheme is on actual demonstrable performance by utilities in terms of sustained AT&C loss reduction.
R-APDRP: The Government approved The Re-structured APDRP during the XI Five Year Plan as a Central Sector Scheme on 31st July-08. PFC is the nodal agency for operationalising the programme. The focus of the programme is on actual, demonstrable performance in terms of loss reduction. Establishment of reliable and automated systems for sustained collection of accurate base line data, and the adoption of Information Technology in the areas of energy accounting will be necessary pre-conditions before sanctioning any projects for strengthening & up-gradation of sub-transmission and distribution networks .Projects under the scheme to be taken up in Two Parts. The activities to be covered under each part are as follows:
· Under Part-A of the Re-Structured APDRP 1401 projects worth of Rs.5648.58 (including 18 Nos SCADA Projects worth Rs.471.58 Crore) to cover almost the entire country for establishment of IT enabled Baseline System have been approved by the GOI.
· Under Part–B, 775 projects worth Rs.14854.43 Crore for strengthening of sub- transmission distribution system, against 1118 eligible towns in the country have also been sanctioned so far.
The Aggregate Technical & Commercial (AT&C) losses in the country have reduced from 30.62% in 2006-07 to 28.44% in 2008-09.
A strategic Blueprint for the 12th Plan has been prepared by the Ministry of Power keeping in view the development of the Power Sector in line with a strategy for low carbon growth. This would enable environment friendly development of the Sector. The said Blueprint has been submitted to the Planning Commission.
13. Renewable Energy Promotion
The promotion of renewable energy is one of the important objectives in the Act. The National Action Plan for Climate Change (NAPCC) envisages the Renewable Purchase Obligation (RPO) to reach 15% in year 2020.
Almost all states have introduced Renewable Purchase Obligations. Renewable Energy Certificates mechanism has been introduced to overcome the geographical limitations of RE generation.
CERC has also created a facilitative framework for grid connectivity and evacuation for renewable.
Problems
Faced and Remedial Action Taken by the Government
1.
Discom Financial
Viability and persisting problems
Tariff revisions are not being done at regular intervals or petitions for revision of Annual Revenue Requirement are not being regularly filed by Discoms. Inadequate tariffs and short term loans for buying power in short term market is deteriorating the financial condition of discoms.
2.
Implementation of
open access at intra-state level
Some states invoked Section 11 of Electricity Act to disallow open access to the generators within the state. As per the Electricity Act 2003, Section 11 is meant to be invoked only in extraordinary circumstances.(e.g. threat to security of state, public order, natural calamity etc.) and is not meant to restrict open access.
The Ministry of Power has filed SLP against the Karnataka High Court judgment upholding the Orders issued by the State Government of Karnataka under section 11 of the Act restricting open access. The matter is sub-judice.
***********