Annexure -II |
||||
|
WORK IN PROGRESS |
||||
|
S.N. |
Name of Schemes |
Amount Sanctioned (Rs. in crores) |
Progress made upto 31.07.2011 |
The time by which
likely to be completed |
|
1 |
2 |
4 |
5 |
5 |
|
NORTHERN REGION |
||||
|
1 |
CHANDIGARH |
|
|
|
|
|
Development of Chandigarh International Airport Ph-I, Mohali |
452.00 |
|
Dec-11 |
|
2 |
JAISALMER |
|
|
|
|
|
Construction of apron and link taxi track
including modification of terminal building |
81.00 |
73% |
Dec-11 |
|
|
|
|
|
|
|
|
|
|
|
|
|
3 |
JAMMU |
|
|
|
|
|
Extension of Apron |
15.00 |
9.5% |
March-12 |
|
4 |
KHAJURAHO |
|
|
|
|
|
Construction of New Terminal Building |
75.32 |
29% |
December-11 |
|
5 |
LUCKNOW |
|
|
|
|
|
Construction of New Integrated Terminal Building |
129.38 |
93% |
September-11 |
|
EASTERN REGION |
||||
|
6 |
NSCBI AIRPORT, KOLKATA |
|
|
|
|
|
Construction of Integrated Terminal Building
including face-lifting of terminals. |
|
|
|
|
|
(a) Terminal Building works |
1612.08 |
74% |
April, 2012 |
|
|
(b) Extension of secondary runway, construction
of taxi track, apron, lighting aids, apron lighting, parking bays, bridges,
apron, etc. |
100 |
98% |
December, 2011 |
|
7 |
RANCHI |
|
|
|
|
|
Construction of New Integrated Passenger Terminal
Building |
137.79 |
86% |
December-11 |
|
8 |
BHUBANESWAR |
|
|
|
|
|
Construction of New Integrated Passenger Terminal
Building |
145.54 |
40% |
April-12 |
|
9 |
PORTBLAIR |
|
|
|
|
|
Construction of Hangar, Annexe Building, Apron
and Link Taxiway etc. |
5.34 |
21% |
September-11 |
|
10 |
PATNA |
|
|
|
|
|
Re-carpetting of
Runway, taxiway & apron and allied works at JPNI Airport. |
23.08 |
99.5% |
August-11 |
|
11 |
RAIPUR |
|
|
|
|
|
Construction of New Expandable Modular Integrated
Terminal Building. |
135.72 |
82% |
December-11 |
|
NORTH EASTERN REGION |
||||
|
12 |
AGARTALA |
|
|
|
|
|
Construction of Control Tower |
9.67 |
46% |
December-11 |
|
13 |
DAPARIZO |
|
|
|
|
|
Construction of Daparizo
Airport |
|
|
|
|
14 |
ITANAGAR |
|
|
|
|
|
Construction of New Airport |
812.00 |
|
48 months after award
of work |
|
15 |
IMPHAL |
|
|
|
|
|
Construction of New Apron |
11.83 |
46% |
September-11 |
|
16 |
PAKYONG |
|
|
|
|
|
Construction of New Airport at Pakyong, Sikkim. |
309.00 |
48.5% |
December-12 |
|
17 |
TEZU |
|
|
|
|
|
Extension and strengthening of runway,
construction of apron and terminal building along with allied structure. |
79.00 |
|
June-13 |
|
WESTERN REGION |
||||
|
18 |
JALGAON |
|
|
|
|
|
Construction of runway, taxi track and parking
bays |
61.00 |
80% |
Nov-11 |
|
19 |
GONDIA |
|
|
|
|
|
Extension of Runway |
42.19 |
4% |
March-12 |
|
|
Construction of IInd
module of Passenger launge |
12.97 |
25% |
November-12 |
|
20 |
GOA |
|
|
|
|
|
New International Terminal, Car Park, Extension
of Apron and Allied Works |
330.02 |
21% |
December-12 |
|
21 |
VADODARA |
|
|
|
|
|
Construction of New Terminal Building
|
115.97 |
1% |
October-12 |
|
SOUTHERN REGION |
||||
|
22 |
CHENNAI AIRPORT, CHENNAI |
|
|
|
|
|
Development of Kamraj Domestic
Terminal, expansion of Anna International and face-lifting of existing
terminal |
|
|
|
|
|
(a) Terminal Building works |
1212.06 |
77% |
December, 2011 |
|
23 |
AGATTI |
|
|
|
|
|
a) Strengthening of runway at Agatti |
11.26 |
|
Completed |
|
|
b) Development of Agatti
Airport |
|
|
|
|
24 |
CUDDAPAH |
|
|
|
|
|
Construction of New Modular Terminal Building |
40.40 |
40% |
December-11 |
|
25 |
PUDUCHERY |
|
|
|
|
|
Construction of Passenger Terminal Building |
29.87 |
30% |
December-11 |
|
26 |
RAJAMUNDARY |
|
|
|
|
|
Construction
of New Terminal Building including Car Park |
43.29 |
95% |
September-11 |
|
27 |
TIRUPATI |
|
|
|
|
|
Construction of New Apron |
174.00 |
46.4% |
March-12 |
|
|
Construction of New Integrated Terminal Building |
0.1% |
February-13 |
|