Annexure-I

WORK COMPLETED DURING LAST THREE YEARS.

Rs. in crores

S. No.

Name of Schemes

Amount  Sanctioned

Status as on 31.07.2011

1

2

3

4

 

NORTHERN REGION

 

 

1

DEHRADUN

 

 

 

Construction of New TB, Substation cum AC Plant room, car park etc.

35.00

Completed

 

Construction of technical block cum control tower, fire station, medical centre

6.78

Completed

2

CHANDIGARH

 

 

 

Construction of New integrated Terminal Building

78.00

Completed

3

LUCKNOW

 

 

 

Construction of new apron for four wide-bodied aircraft and taxiway.

41.30

Completed

4

SRINAGAR

 

 

 

Expansion of apron Ph-II

28.00

Completed

 

Expansion and Modification of Terminal Building complex.

101.33

Completed

5

VARANASI

 

 

 

Construction of new integrated terminal building complex

139.50

Completed

 

Extension and strengthening of apron and extension of runway.

40.00

Completed

6

JAIPUR

 

 

 

Construction of new international terminal complex

115.77

Completed

 

Construction of new apron and taxiway

32.00

Completed

7

UDAIPUR

 

 

 

Extension and strengthening of runway and allied works

44.31

Completed

 

Construction of control tower & technical block

9.38

Completed

 

Construction of new terminal building complex

77.44

Completed

 

Construction of Apron including  link Taxiway- Ph II

7.76

Completed

8

JAISELMER

 

 

 

Construction of Apron & Link taxi track

9.94

Completed

9

AMRITSAR

 

 

 

Modular Expansion of Terminal Building (Ph-II)

117.36

Completed

 

Strengthening/Resurfacing of runway and apron /  taxiway

9.80

Completed

 

EASTERN REGION

 

 

10

RANCHI

 

 

 

Expansion of apron and construction of isolation bay

12.52

Completed

 

Resurfacing of Runway

15.07

Completed

11

COOCH BEHAR

 

 

 

Construction of new terminal building

12.50

Completed

12

PORTBLAIR

 

 

 

Expansion of apron and additional taxiway.

34.38

Completed

13

PATNA

 

 

 

Re-carpeting of runway, taxiway & apron and allied works at

23.08

Completed

 

JPNI Airport.

 

 

 

NORTH-EAST REGION

 

 

14

AGARTALA

 

 

 

Expansion and strengthening of apron

18.66

Completed

 

Strengthening of existing runway

37.00

Completed

15

DIBRUGARH

 

 

 

Construction of new terminal building i/c land acquisition.

71.71

Completed

 

Strengthening of existing runway  and taxiway

17.71

Completed

16

BAGDOGRA

 

 

 

Extension of apron

20.70

Completed

17

GUWAHATI

 

 

 

Extension of runway and C/o new apron with link taxiway, 

60.82

Completed

 

Construction of isolation aircraft parking stand.

14.15

Completed

 

C/o B. wall in the newly acquired land for r/w extn. And c/o new apron

8.95

Completed

 

Filling of the Newly Acquired Area for International Terminal Building (Ph-I)

29.78

Completed

18

SILCHAR

 

 

 

Extension of runway, acquisition of land & const. of boundary wall.

41.50

Completed

19

BARAPANI (SHILLONG)

 

 

 

Construction of new Terminal Building.

29.70

Completed

 

WESTERN REGION

 

 

20

AHMEDABAD

 

 

 

C/o New International Terminal Building

328.00

Completed

 

C/o New International Terminal Building Phase-II

Completed

 

Expansion of existing Apron at Ahmedabad.

10.96

Completed

21

BHOPAL

 

 

 

Extension & strengthening of runway and associated work

52.10

Completed

 

Construction of new apron and associated works

63.78

Completed

 

Construction of New Expandable Modular Terminal Building at Raja Bhoj Airport, Bhopal.

135.00

Completed

22

INDORE

 

 

 

Construction  of New Integrated Terminal building

135.60

Completed

 

Extension & strengthening of runway

79.00

Completed

23

AURANGABAD

 

 

 

Construction of new terminal building, Technical Block, Control Tower, Fire Station, MT etc

99.70

Completed

 

Extension of  runway including electrical works

25.68

Completed

24

NAGPUR

 

 

 

Exp. & mod. of Terminal Bldg. for international operations

43.00

Completed

25

PUNE

 

 

 

Ext. & Modification of Terminal Building

78.00

Completed

 

Ext. & Str. of existing apron and taxi-track Phase II at Pune Airport.

15.42

Completed

 

Construction of Pallaral Taxiway

 

Completed

26

GONDIA

 

 

 

Construction of New Passenger Lounge, Control Tower, Fire Station,  Boundary Wall, Residential Quarters and other Ancillary  Works

41.75

Completed

 

Extension & Strengthening of Runway

40.95

Completed

 

Construction of Parallel Taxi way

18.32

Completed

 

Construction of NIATAM

52.33

Completed

27

GOA

 

 

 

Construction of New apron for new international terminal building

14.86

Completed

28

VADODARA

 

 

 

Construction of Maintenance & Night parking stand with associated works

17.12

Completed

29

SURAT

 

 

 

Development of Surat Airport for ATR-72 type Aircraft -Terminal Bldg work.
A/A & E/S Amt:- 49.41 crores
Likely completion cost:-53.33 crores

53.33

Completed

 

Extension of Runway
A/A & E/S Amt:- 19.40 crores
Likely completion cost:-21.30 crores

21.30

Completed

 

Construction of Terminal Building Ph-II first floor
A/A & E/S Amt:- 23.68 crores
Likely completion cost:-19.50 crores

23.68

Completed

 

SOUTHERN REGION

 

 

30

CHENNAI AIRPORT, CHENNAI

 

 

 

a) Extension of secondary runway, parking bays, bridges, apron, etc.

230.86

Completed

 

b) Construction of RCC/prestressed concrete bridge for aircraft movement across the Adyar river.

207.14

Completed

31

COIMBATORE

 

 

 

Construction of part parallel taxiway and Expansion of apron

41.51

Completed

 

Expansion & Modification of Terminal Building

78.00

Completed

32

AGGATTI

 

 

 

Strenthening of Runway

12.80

Completed

33

VIZAG

 

 

 

C/o new integrated TB

94.95

Completed

34

PUDUCHERRY

 

 

 

Development of Puduchery Airport
SH: Construction of Runway

24.34

Completed

35

MYSORE

 

 

 

Development of Mysore Airport Building work

69.29

Completed

36

VIJAYWADA

 

 

 

Extension and strengthening of runway Construction of new apron

48.00

Completed

37

CUDDAPAH

 

 

 

Construction of runway,taxiway, apron & allied works

26.12

Completed

38

CALICUT

 

 

 

Resurfacing of Runway and widening shoulder for B-747 incl gradingof balance area of runway

27.00

Completed

39

TRIVANDRUM

 

 

 

Construction of New International Terminal Complex across the runway on Chackai side.
(a) C/o NITB and other services

245.58

Completed

 

Construction of  8 nos bays,taxiway,GSE area & shoulders.

30.92

Completed

40

MANGALORE

 

 

 

Construction of New Terminal Building i/c apron

147.00

Completed

 

Construction of apron

Completed

41

MADURAI

 

 

 

Construction of new integrated terminal building

128.76

Completed

 

Strengthening & extnesion of runway

35.25

Completed

42

TRICHY

 

 

 

C/o New Terminal Bldg.

74.70

Completed

 


 

Annexure -II

WORK IN PROGRESS

S.N.

Name of Schemes

Amount Sanctioned     (Rs. in crores)

Progress made upto 31.07.2011

The time by which likely to be completed

1

2

4

5

5

NORTHERN REGION

1

CHANDIGARH

 

 

 

 

Development of Chandigarh International Airport Ph-I, Mohali

452.00

 

Dec-11

2

JAISALMER

 

 

 

 

Construction of apron and link taxi track including modification of terminal building

81.00

73%

Dec-11

 

 

 

 

 

 

 

 

 

 

3

 JAMMU

 

 

 

 

Extension of Apron

15.00

9.5%

March-12

4

KHAJURAHO

 

 

 

 

Construction of New Terminal Building

75.32

29%

December-11

5

LUCKNOW

 

 

 

 

Construction of New Integrated Terminal Building

129.38

93%

September-11

EASTERN REGION

6

NSCBI AIRPORT, KOLKATA

 

 

 

 

Construction of Integrated Terminal Building including face-lifting of terminals.

 

 

 

 

(a) Terminal Building works

1612.08

74%

April, 2012

 

(b) Extension of secondary runway, construction of taxi track, apron, lighting aids, apron lighting, parking bays, bridges, apron, etc.

100

98%

December, 2011

7

RANCHI

 

 

 

 

Construction of New Integrated Passenger Terminal Building

137.79

86%

December-11

8

BHUBANESWAR

 

 

 

 

Construction of New Integrated Passenger Terminal Building

145.54

40%

April-12

9

PORTBLAIR

 

 

 

 

Construction of Hangar, Annexe Building, Apron and Link Taxiway etc.

5.34

21%

September-11

10

PATNA

 

 

 

 

Re-carpetting of Runway, taxiway & apron and allied works at JPNI Airport.

23.08

99.5%

August-11

11

RAIPUR

 

 

 

 

Construction of New Expandable Modular Integrated Terminal Building.

135.72

82%

December-11

NORTH EASTERN REGION

12

AGARTALA

 

 

 

 

Construction of Control Tower

9.67

46%

December-11

13

DAPARIZO

 

 

 

 

Construction of Daparizo Airport

 

 

 

14

ITANAGAR

 

 

 

 

Construction of New Airport

812.00

 

48 months after award of work

15

IMPHAL

 

 

 

 

Construction of New Apron

11.83

46%

September-11

16

PAKYONG

 

 

 

 

Construction of New Airport at Pakyong, Sikkim.
(SH: Earth work in cutting and filling, geogrid reinforced retaining wall, drainage system including box culvert, aerodrom pavement etc)

309.00

48.5%

December-12

17

TEZU

 

 

 

 

Extension and strengthening of runway, construction of apron and terminal building along with allied structure.

79.00

 

June-13

WESTERN REGION

18

JALGAON

 

 

 

 

Construction of runway, taxi track and parking bays

61.00

80%

Nov-11

19

GONDIA

 

 

 

 

Extension of Runway

42.19

4%

March-12

 

Construction of IInd module of Passenger launge

12.97

25%

November-12

20

GOA

 

 

 

 

New International Terminal, Car Park, Extension of Apron and Allied Works

330.02

21%

December-12

21

VADODARA

 

 

 

 

Construction of New Terminal Building

115.97

1%

October-12

SOUTHERN REGION

22

CHENNAI AIRPORT, CHENNAI

 

 

 

 

Development of Kamraj Domestic Terminal, expansion of Anna International and face-lifting of existing terminal

 

 

 

 

(a) Terminal Building works

1212.06

77%

December, 2011

23

AGATTI

 

 

 

 

a) Strengthening of runway at Agatti

11.26

 

Completed

 

b) Development of Agatti Airport

 

 

 

24

CUDDAPAH

 

 

 

 

Construction of New Modular Terminal Building

40.40

40%

December-11

25

PUDUCHERY

 

 

 

 

Construction of Passenger Terminal Building

29.87

30%

December-11

26

RAJAMUNDARY

 

 

 

 

Construction  of New Terminal Building including Car Park

43.29

95%

September-11

27

TIRUPATI

 

 

 

 

Construction of New Apron

174.00

46.4%

March-12

 

Construction of New Integrated Terminal Building

0.1%

February-13