ANNEXURE

ANNEXURE REFERRED TO IN REPLY TO PART  (A) to (C) OF RAJYA SABHA UNSTARRED QUESTION NO. 408 TO BE ANSWERED ON 24TH FEBRUARY 2011 ASKED BY SHRI. K.N. BALAGOPAL

Sl. No

Name

NH No

Length in km

Present status of execution

1

Thiruvananthapuram Neyyattinkara bypass

47

44.493

2 lane bypass  for part length of  22.633km has been completed.  The  balance length is held up since land acquisition  is presently stopped by Govt. of Kerala. The four lane bypass including the balance length under NHDP Phase-III can be taken up after the land acquisition is completed.

2

Alappuzha Bypass

47

7.580

2 lane bypass for part length of 6.035 km is completed. DPR is under preparation for the 4 laning including the balance works.

3

Kollam Bypass

47

13.141

2 lane bypass for part length of 4.791 km is completed. DPR is under preparation for the balance length.

4

Attingal Bypass

47

85.57

 

In view of Land Acquisition problems in Kerala, the bids were cancelled by NHAI. Bids will be re-invited once land acquisition issue is  resolved by the Government of Kerala.

5

Kodungallur Bypass

17

3.75

Construction work for 4 lane bypass has commenced. The likely date of completion is 07-01-2012

6

Thalasery-Mahe Bypass

17

18.031

Work for 4 laning is awarded and Concession Agreement signed on 24.02.2010 by NHAI as a part of NHDP Package.  Work is held up due to stoppage of land acquisition by Government of Kerala.

7

Kozhikode bypass

17

28.12

 2 lane bypass  for part length of 16.164km is completed.

4 lane bypass including the balance length has been awarded and Concession Agreement signed on 24.02.2010 by NHAI as part of NHDP package. Work is held up due to stoppage of land acquisition by the Government of Kerala.

8

Koilandy Deviation/ bypass

17

    12

4 lane bypass awarded and Concession Agreement signed on 24.02.2010 by NHAI as a part of NHDP package. Work is held up due to stoppage of land acquisition by Government of Kerala.

9

Payyannyur bypass

17

24.1

4 lane bypass awarded and Concession Agreement signed on 13.05.2010 by NHAI as a part of NHDP package. Work is held up due to stoppage of land acquisition by Government of Kerala.

 

10

Taliparamba bypass

 

17

5.6

11

Kannur Bypass

17

19

4 lane bypass awarded and Concession Agreement signed on 24.02.2010 by NHAI as a part of NHDP package. Work is held up due to stoppage of land acquisition by Government of Kerala.

12

Kottakal Edarikkode  Bypass

17

4.50

13

Valanchery Bypass

17

4.30

14

Ponnani bypass

17

20.87

These bypasses are included in the package of NHDP of 4 laning from Kuttipuram to Edapally section by NHAI. Due to lack of response in bidding under BOT(Toll) bids were invited on BOT( annuity) basis. However the proposals are held  up due to stoppage of Land Acquisition activities by Kerala Govt.

 

 

 

 

15

Chavakkad Bypass

17

2.2

16

Vadanappally Bypass

17

3.2

17

Triprayar- Valappad Bypass

17

3.35

18

Chendrappinni Bypass

17

1.9

19

Moonnupeedika

17

1.95

20

Mathilakam Bypass

17

4.86

21

Paravur Bypass

 

17

11.71

22

Edapally

Bypass

17

3.6

23

Thripunithura Bypass

 

 

49

 

 

8.8

 

 

Alignment finalized for part length of 3.75km  and Land Acquisition is  in progress. Alignment for balance length is under finalization by Government of Kerala. The construction of bypass would be taken up after completion of land acquisition.

24

 Thamarassery Bypass

212

3.20

 These bypasses are part of Kozhikode –Muthanga project to be implemented under NHDP-IVA. Bids for these bypasses are being  taken up by the State PWD of Kerala.

25

Sulthan Bathery Bypass

212

4.30

 

*****