STATUS OF DEVELOPMENT OF 35 NON METRO AIRPORTS
[As on Jan. 2011]
S. No. |
Airport |
City Side/Terminal Building works |
Air side works |
Remarks |
1. |
Agra (Uttar Pradesh) |
-Renovation of Terminal
Building.- work completed |
-Expansion of Apron- Work completed. |
|
2. |
Agartala (Tripura) |
-Construction
of Technical Block- work completed. |
-Expansion of Apron. -Strengthening of existing runway – Work completed |
|
3 |
Ahmedabad (Gujarat) |
-Domestic (Arr/Dep) – Completed. New
International Terminal Building to handle 1600 passengers commissioned on 15th
July, 2010. Subway Pedestrian walk way linking International
Terminal & Domestic Terminal commissioned on 15th July, 2010. -New Control Tower cum Tech Block – Planning
Stage |
New International Apron – completed. Extension of Domestic Apron – Completed. -Construction of part parallel taxi track |
67 acres of Land requisitioned from S/ Govt.) |
4 |
Amritsar (Punjab) |
-Construction of New Terminal Building- work
completed. -Modular expansion of Terminal Building Phase II
– Work completed. |
-Extension of runway- work completed. -Expansion of apron for additional four bays –
Civil work completed. |
Put into operation Put into operation. |
5 |
Aurangabad (Maharashtra) |
-New Integrated Terminal Building- work
completed. Installation of 2 no’s passenger Boarding Bridges- work
completed. |
-New Apron- work completed. -Strengthening & extension of of runway-work
completed. |
Put in operation in April, 09 |
6 |
Bhopal (Madhya Pradesh) |
-Construction of new Expandable Modular
Integrated Terminal Building –Work completed on31st Jan. 2011. Likely to be
operationalise in Feb. 11. |
- Extension of runway- work completed. -New Apron with link taxiway & expansion of
isolation bay –PDC January, 2011. |
|
7. |
Bhubaneswar (Orissa) |
-Construction of Domestic Terminal Building - Tender awarded PDC April-2012 |
-Expansion of apron – work completed. |
|
8. |
Calicut (Kerala) |
-Extension & modification of the
international & domestic terminal building – Work Completed. |
-Strengthening & expansion of existing Runway
– work completed except EMAS (Engineered Material Arresting System). |
|
9. |
Chandigarh |
-Construction of New Terminal Building – Work
completed. |
|
Operationalised wef 15.11.2010 |
10 |
Coimbatore (Tamil Nadu) |
-Expansion & modification of existing
Terminal building – PDC March, 2011. -Construction of new Integrated Terminal Building
– Planning stage. |
-Construction of part parallel taxiway, extension
of Apron – Work completed -Strengthening of old apron and allied works –
completed. -Extension of runway – Planning stage. |
Subject to hand over of additional land by State
Govt. |
11. |
Dehradun (Uttrakhand) |
-Construction of new Terminal building – work
completed. |
-Strengthening and extension of runway- work
completed. -Construction of apron - work
completed. |
|
12 |
Dibrugarh (Assam) |
-Terminal Building – Work completed |
-New apron work completed. Runway strengthening – PDC January, 2011 -Extension of runway – Kept in abeyance due to
want of land from the Army. |
|
13 |
Goa |
-Construction of new integrated terminal building
. |
-Construction of parallel taxi track. Two link
taxi tracks -Two rapid exit taxiways. |
|
14 |
Guwahati (Assam) |
-Modification to the existing Terminal Building
–work completed. -Construction
of International Terminal building – Planning stage. |
-Extension of Runway, apron, Isolation Bay – work completed -Construction of parallel taxi track- Planning
stage. |
NOC from IAF awaited. |
15 |
Indore (Madhya Pradesh) |
Construction of Integrated Terminal building –
PDC Jan, 2011 |
-Extension of runway, -Construction of New Apron and
link taxiway - completed. |
|
16 |
Imphal (Manipur) |
-Modification of Terminal Building – September,
2011 |
-Expansion of apron and link taxiway – PDC Aug, 2010 |
|
17 |
Jaipur (Rajasthan) |
-New International building – Completed -Expansion of new International Terminal Building
– Planning stage. |
-Construction of new apron, link taxi track and
part parallel taxi track – completed. -Extension of runway- Planning stage. |
Commissioned on 1st July, 09. |
18 |
Khajuraho (Madhya Pradesh) |
-Construction of terminal building- PDC June,
2011. |
-Construction of new apron, link taxi track –
Completed. |
Contract rescinded due to non performance of
agency. Fresh tender being called. |
19 |
Lucknow (Uttar Pradesh) |
-Construction of new international terminal
building, car park- PDC June, 2011. |
-Construction of new apron/Expansion of existing
apron, rapid taxi track, parallel taxi track- Completed |
|
20 |
Madurai (Tamil Nadu) |
-Construction of new integrated terminal building
complex – Work completed 27th July, 2010. -Control Tower cum Technical Block – Planning
stage. |
-Extension of runway, new
apron- Completed. -Parallel taxi track – Planning stage. |
Subject to availability of additional land by
State Govt. |
21 |
Mangalore (Karnatka) |
-Construction of a new Integrated Terminal
Building-Completed |
-Extension of Runway –Completed. |
|
22 |
Mysore (Karnatka) |
-Construction
of Terminal Building, Tech Block cum control tower, Fire Station etc-Work
Completed. |
-The work for construction of Runway-work completed Runway extension- -Planning stage |
Subject to balance availability of land from S/Govt. |
23 |
Nagpur (Maharashtra) |
-Construction
of New international arrival hall + -Expansion of existing Terminal Building
–Completed. |
-Provision of New Tech. Block cum Control Tower- Planning stage. |
|
24 |
Port Blair |
-New integrated terminal building – Planning
stage. |
-Expansion and strengthening of apron - Completed |
|
25 |
Pune (Maharashtra) |
- Lateral expansion of terminal building to make
it an integrated terminal building for 800 passengers. |
-Construction of parallel taxi track and
expansion of apron – completed. |
Major area of the building except airside corridor have been put in
operation (94% work completed) |
26 |
Raipur (Chhattisgarh) |
- Construction of new integrated terminal
building to cater to 700 passengers at a time (300 Intnl. + 400 Dom.) with
two aerobridges – PDC Jan, 2011. - Development of
the airport for wide bodied aircraft operations – Planning Stage |
-Runway Extension and new apron
– Completed. |
Subject to 2440 acres of land is made available by state Govt.&
traffic demand. |
27 |
Ranchi (Jharkhand) |
- Construction of new integrated terminal
building to cater to 700 (250 arr. + 250 dep.) domestic & (100 arr. + 100
dep.) international passengers with two aerobridges – PDC March, 2011.
|
-Expansion/Strengthening of apron –Completed |
|
28 |
Srinagar (Jammu & Kashmir) |
-Expansion
& modification of Terminal Building – Completed. |
-Expansion of apron work completed. -Construction of cargo complex – Planning Stage -Expansion of car park. |
|
29 |
Surat (Gujarat) |
-New Terminal Building - completed |
-Extension of Runway & apron – completed. |
|
30. |
Trivandrum (Kerala) |
-Construction of new International terminal
building – Completed. |
-Part parallel taxi track – Work Completed. |
State Govt. related works pending. |
31. |
Trichy (Tamilnadu) |
-Construction of new integrated terminal building
– Completed. |
-Extension of runway- Completed |
Subject to provision of land, to be acquired. |
32 |
Udaipur (Rajasthan) |
-Construction of new terminal building – Work Completed. -Construction of Technical Block and Control
Tower- Work completed. Control Tower inaugurated on 26th Jan,
2010. Tech Block in August, 2010. |
-Construction of new apron, link taxi track,
isolation bay (Phase I) - Completed. (Phase II) PDC 15th April,
2011. -Extension of runway –work completed. |
|
33 |
Vishakha- Patnam (Andhra Prad.) |
-Construction of new integrated terminal building
– Completed |
-Apron - completed |
|
34 |
Varanasi (Uttar Pradesh) |
-Construction
of new integrated terminal building – Work completed. NITB Operationalised
w.e.f 15.11.2010. |
-Extension of runway- Completed. -Expansion of apron – work completed |
|
35 |
Vadodara (Gujarat) |
-New integrated terminal building complex –
Tender stage. |
-Apron for night parking – Completed -Construction of parallel taxiway- Planning stage. |
|
STATUS OF DEVELOPMENTS OF OTHER 13
AIRPORTS.
[As on Jan, 2011]
S.No |
Airport |
City Side/Terminal Building works |
Air side works |
Remarks |
1 |
Agatti/ Lakshadweep |
Construction of New Terminal Building. – work
completed. Technical Building cum control tower & fire
station- work completed. Extension of runway, construction of new apron,
Relocation of terminal building, Control Tower/Tech. Block - Planning Stage |
Runway Extension, Construction of new Apron–work
completed. |
Dep. Block completed. Arr. Block work deferred due Rwy extension. . Subject to provision of additional land by Lakshadweep Administration. |
2 |
Akola (Maharashtra) |
Modification of existing terminal building and
other allied buildings- Work completed. Construction of control tower & Tech
Block-planning stage. |
Runway
extension-Planning stage. Expansion of apron-
Completed. |
Subject to land to be acquired from State Govt. |
3 |
Belgaum (Maharashtra) |
Expansion & modification of existing terminal
building- Work Completed. Construction of New Terminal Building – Planning stage. |
Extension of runway. Planning stage. |
Subject to signing of MOU and availability of
additional land from State Govt. |
4 |
Cooch Behar (West Bengal) |
Construction of new Terminal Building – Work Completed. . |
Runway strengthening work completed. |
28.86 acres of land including strip of 600mx200m across the river
handed over by state Govt. Est. are under preparation |
5 |
Dimapur (Nagaland) |
Scope of
work for face lifting of Terminal Building, and city Side developments are
being finalized. |
Expansion of apron and construction of link taxiway – PDC April, 2011. |
|
6 |
Gondia (Maharashtra) |
Construction of New Terminal Building –
Completed. Passenger lounge (for 25 passengers), Fire
Station, Residential Quarters – completed. |
Construction of 1 hanger – Completed. Fire Station, Boundary wall, Control Tower– Completed. Extension of runway, part parallel taxi track –completed. |
|
7 |
Hubli (Karnatka) |
Expansion & modification of existing Terminal
Building- work completed. Construction of new Terminal Building- Planning
stage. |
Runway extension subject to availability of land-Planning Stage |
Subject to signing of MOU and availability of land from SG. |
8. |
Jammu (Jammu & Kashmir) |
Modification of terminal building-Dec., 2010. (Planning stage). Construction of new civil air terminal
complex.-Planning stage subject to land acquisition from State Govt. |
Extension of Runway and expansion of apron –
Planning Stage. |
Pending due to land acquisition from army. |
9 |
Kullu (Himachal) |
Construction of new terminal building – work
completed. |
Resurfacing of runway. Construction of new Apron and taxiway. |
|
10. |
Patna (Bihar) |
Construction of New Terminal Building, Isolation
Bay & New Fire Station- Planning stage. |
|
Subject to availability of additional land from
State Govt. |
11 |
Rajahmundry (Andhra Pradesh) |
Construction of new Terminal Building-PDC March,,
2011 |
Extension of Runway-Planning Stage |
Subject to availability of land from State Govt |
12 |
Rajkot (Gujarat) |
Construction of new terminal - Planning stage. |
Extension of Runway –Planning stage. |
(Subject to required land 21 Hectares is made
available by Railway Board and diversion of Rajkot-Jamnagar highway by State
Govt.) |
13 |
Vijayawada (Andhra Pradesh) |
New Terminal Building-Planning Stage |
extension & strengthening of runway-Work
completed |
|
Additional 10 Airports [As on Jan. 2011]
Tirupati (Andhra
Pradesh)
Strengthening of Rwy
& extension of Apron |
Work completed. |
Installation of ILS |
Work completed |
New Integrated Terminal
Building |
Planning stage |
Tuticorin (Tamil Nadu)
Extension of Rwy & associated facilities for the operation of
AB-320 class of aircraft |
Planning stage. Master
plan forwarded to Govt of Tamil Nadu for additional land requirement of 650
Acres. |
Pondicherry (U.T.)
Extension & strengthening of Rwy for dimension 150m x 45m for ATR72
type of aircraft and subsequently for AB-320 type of aircraft operation with
associated facilities including Apron, including widening of basic strip to
300m. |
MOU signed. Govt of
Puducherry handed over 50acres of land on the eastern side of the airport for
the extension of the Rwy for ATR72 type of aircraft operation. Govt of
Puducherry is being pursued to hand over remaining land. Work order issued for extension and
strengthening of runway for ATR 72 operations for Rs 19.80 Crores. Work completed. |
Bagdogra (West Bengal)
Phase I Expansion of Apron for
parking of 4(A-321),1(IL-76) & 2 Helicopter parking. |
Work Completed. |
Jaisalmer (Rajasthan)
Construction of New
Apron for 3 parking stands – C Type Construction of New Terminal Building. |
Work in Progress,
Progress 15%. Planning stage. |
Silchar (Assam)
Runway extension on
either end upto 7500 ft |
Work completed. |
Cuddapah (Andhra
Pradesh)
Construction of Runway,
Apron, Taxiway, Compound wall and allied works |
Runway & apron
works completed, for ATR72 type of aircraft operation. Pre-fabricated
Terminal building, technical block cum control tower and fire station in
final stage. Tender under process. |
Warangal (Andhra
Pradesh)
Development of Airport for ATR type of
aircraft operations . |
MOU with Govt. of
Andhra Pradesh signed in 2007. Projected the additional land requirement of
438 acres to Govt. of AP in 2008. Land transfer awaited. |
Pantnagar (Uttrakhand)
Runway extension to
cater for ATR 72 type of aircraft, Renovation of Terminal Building and
Provision of Ground Lighting completed. |
Work completed |
Leh (Jammu &
Kashmir)
·
Construction of Civil Apron, Car Park ·
Construction of New Terminal Building |
Work completed. Drawing finalized. Land transfer from IAF
awaited. |