Annexure referred to in reply to Rajya Sabha USQ No. 1538 for 9/3/2011.
ANNEXURE-A
State-wise Metro Rail Project their length,
estimated cost and funding pattern (Abbreviations are explained after the table)
S No. |
Project |
Length (km.) |
Cost (Rs.in
crore) |
Fund Sharing Pattern (Rs.in
crore) |
1. |
|
65.05 |
10571 |
Equity
GoI- 1464.00 Equity
GNCTD- 1464.00 Sub.Debt GoI- 252.00 Sub.Debt GNCTD- 252.00 JICA
loan through GoI 6839.00 Property
development- by
DMRC 300.00 ------------------- Total
- 10571.00 |
2. |
Delhi MRTS Phase II |
54.68 |
11691.36 |
Equity
GoI - 2459.695 Equity
GNCTD- 2459.695 Sub.Debt GoI- 175.000 Sub.Debt GNCTD-
175.000 JICA
loan- 5056.970 through
GoI Property
development- 960.000 by DMRC Internal accrual- 405.000 by DMRC Total - 11691.360 |
3. |
Extension of Ambedkar Nagar in |
14.47 |
1589.44 |
Haryana portion Land
GoH- 20.00 Grant
GoH - 461.85 Grant
GoI 116.59 Rolling
Stock BY DMRC 98.00 ----------------------------- Sub
total- 696.44 Sub.Debt for land GoI - 24.50 Sub.Debt for land GNCTD- 24.50 Equity
GoI - 111.00 Equity
GNCTD- 111.00 Grant
GoH - 111.00 JICA
loan - 352.00 ---------------------- Sub
total -
734.00 Central Taxes Haryana portion as Sub Debt. by GoI - 55.00 GoH - 20.00 --------------------------- Sub
total - 75.00 Central Taxes GoI - 30.00 GNCTD - 30.00 GoH - 24.00
---------------- Sub
total - 84.00 Grand
total - 1589.44 |
4. |
Extension of New Ashok Nagar in |
7.0 |
827.00 |
Land
GoUP - 32.00 Grant
GoUP - 488.80 Grant
GoI - 122.20 Rolling
Stock by DMRC- 93.00
---------------------------------- Sub
total - 736.00 Central Taxes as Sub Debt. by GoI - 69.00 GoUP - 22.00
---------------------- Sub
total - 91.00 Grand
Total - 827.00 |
5. |
Central Secretariat to Badarpur |
20.16 |
4012.00 |
Equity
GoI - 612.50 Equity
GNCTD- 612.50 Sub.Debt GoI 322.00 Sub.Debt GNCTD- 322.00 JICA
loan - 2143.00 --------------------------------------- Total - 4012.00 |
6. |
Metro link from Dwarka
Sector-9 to Sector-21 |
2.76 |
356.11 |
Grant
DDA -
275.00 Rolling
Stock by DMRC- 81.11
----------------- Total 356.11 |
7. |
Airport Metro Express Link |
19.2 3.50 |
3076.00 793.00 |
Equity
GoI - 599.00 Equity
GNCTD- 599.00 Equity
Concessionaire- 461.00 Debt
Concessionaire 1067.00
------------------- Total - 3076.00 Equity
GoI - 158.60 Equity
GNCTD - 158.60 Grant
DDA - 217.40 Concessionaire - 77.50 investment Debt
Concessionaire - 180.00 --------------------- Total - 793.00 |
8. |
(KARNATAKA) |
42.3 |
8158.00 |
Equity
GoI - 1223.70 Equity
GoK - 1223.70 Sub.Debt GoI- 815.80 Sub.Debt GoK- 1223.70 JICA
loan through
GoI - 3671.10 ------------------------ Total
- 8158.00 |
9. |
Kolkata East-West Metro Corridor ( |
14.67
|
4874.58 |
Equity
GoI - 701.50 Equity
GoWB- 701.50 Sub.Debt GoI- 467.50 Sub.Debt GoWB- 751.14 JICA
loan - through
GoI 2252.94 --------------- Total
- 4874.58 |
10. |
Chennai Metro (TAMIL NADU) |
45.046 |
14600.00 |
Equity
GoI - 2190.00 Equity
GoTN- 2190.00 Sub.Debt GoI- 730.00 Central
taxes Sub.Debt GoTN- 844.00 JICA
loan - through
GoI 8646.00
--------------- Total - 14600.00 |
11. |
Mumbai Metro Line-1 ( (On Public Private Partnership mode) |
11.0 |
2356.00 |
Equity
Concessionaire- 380.00 Equity
MMRDA- 134.00 Debt
- 1192.00 VGF
grant GoI -
471.00 VGF
grant GoM- 179.00
------------------------------ Total
- 2356.00 |
12. |
Mumbai Metro Line-2 ( (On Public Private Partnership mode) |
31.87 |
7660.00 |
Equity Concessionaire- 1609.00 Debt - 3753.00 VGF grant GoI- 1532.00 VGF grant GoM- 766.00 ------------- Total - 7660.00 |
13. |
Jaipur Metro Stage-I (RAJASTHAN) |
28.918 |
1250.00 |
Equity/Grant/Loan
by Govt. of Rajasthan and its Agencies/Banks etc. Total - 1250.00 |
14. |
(ANDHRA PRADESH) (On Public Private
Partnership Mode) |
71.16 |
12132.00 |
VGF
GoI - 1458.00
Contribution
by
----------------- Total
Cost - 12132.00
|
Abbreviations :-
GoI - Government of
GNCTD - Government of
GoH - Government of Haryana
GoUP - Government of Uttar Pradesh
GoK - Government of Karnataka
GoAP - Government of Andhra Pradesh
GoWB - Government of
GoTN - Government of Tamil Nadu
GoM - Government of
DMRC - Delhi Metro Rail Corporation Ltd.
NCR - National Capital Region
IGI -
DDA -
HUDA - Haryana
Urban Development Authority
MMRDA - Mumbai Metropolitan Regional Development Authority
JICA - Japan International Cooperation Agency
Sub.Debt - Subordinate Debt
VGF - Viability Gap Funding
********
ANNEXURE-B
Statement of Metro Rail Project proposals received
by the Union Government but not sanctioned
S. No. |
Project |
Length (in km) |
Cost (Rs.in
crore) |
Status |
National
Capital Region |
||||
1. |
Extension of (HARYANA) |
13.875 |
2,533 |
Proposal has been recommended 'in principle' by
Empowered Committee in its meeting held on 10.8.2010 |
2. |
Extension of (UTTAR PRADESH) |
2.574 |
320 |
Proposal has been recommended 'in principle' by
Empowered Committee in its meeting held on 10.8.2010. |
3. |
Extension of |
11.781 |
1,432 |
Govt. of Haryana (GoH)
has been advised to submit Comprehensive Mobility Plan, alternative analysis
report, starting of modern city bus service and to address mandatory reforms
along with financial commitment on cost sharing as well as to obtain in
principle approval of GNCTD. |
4. |
|
103.050 |
35,242 (with Central taxes) |
DMRC has submitted revised DPR on 10.2.2011 for
further processing. The DPR has been circulated to Planning Commission
and concerned Ministries/Departments for comments/advice. |
5. |
(KERALA) |
25.3 |
2,991.5 |
Not Sanctioned |
6. |
Colaba-Mahim/Bandra Corridor Line-III ( |
20.4 |
12,000 |
Project
referred to Ministry of Finance for JICA Loan |
7. |
Chennai Metro Rail
Project Phase-II Extension from Washermanpet to WIMCO Nagar (TAMIL NADU) |
9.051 |
3001 |
DPR submitted by Government of Tamil Nadu in
October, 2010 for approval. DPR has
been circulated by MoUD to Planning Commission,
Ministry of Railways, Ministry of Finance for
comments/advice. |
***