ANNEXURE
ANNEXURE REFERRED TO IN REPLY TO PART (a)
to (e) OF RAJYA SABHA UNSTARRED QUESTION NO.2458 TO BE ANSWERED ON 1ST
DECEMBER, 2010 ASKED BY SHRI NARENDRA KUMAR KASHYAP
REGARDING SLOW
PROGRESS OF WORK ON NH-58.
Sl. No. |
NH No. |
Stretch/Section |
Status |
1 |
58 |
Meerut-Muzaffarnagar |
4-laning of Meerut-Muzaffarnagar section
(Km.52.250 to 131.00) of NH-58 was awarded on BOT (Toll) basis with schedule
completion as March, 2009. Out of total length of Reasons for delay: (i) Tree cutting
by the State Forest Deptt. due
to imposition of additional condition of providing 10 mtr.
strip along the highway. (ii) Acquisition of land by the Competent
Authority and removal of encroachments/structures by Distt. Authorities. (iv)
Shifting of utilities and relocation of religious structure. (v)
Slow progress by the Contractor. |
2 |
58 |
Muzaffarnagar- Haridwar from (Km. 131.00 to Km.211.00) |
4-Laning of Muzaffarnagar-Haridwar
Section of NH-58 awarded to concessionaire Era-Sibmost on BOT (Toll) basis.
Agreement signed on 24.02.2010. The work is likely to start by Dec., 2010. |
3 |
58 |
Haridwar-Nepali farm from (Km. 211.00 to Km.218.200) |
4-Laning of Haridwar-Dehradun Section of
NH-58 awarded to concessionaire Era-Sibmost on BOT (Toll) basis. Agreement
signed on 24.02.2010. The work is likely to start by Dec., 2010. |
*****