Annexure-I as referred to in reply to part (a) to (d) of Rajya Sabha Unstarred Question No. 1828 for 25.11.2010

(All figures in Rs. lac)

Sl.No.

Name of Project

Year of DPR submission

Estimated cost

Status

1

2

3

4

5

1.

Construction of Multi Level Vehicle Parking at Old Medical Directorate Site

2008-09

2973.45

Returned to State Government; included in DPR at S.  No. 8

2.

Construction of Multi Level Vehicle Parking at NST Site

2008-09

1987.08

Returned to State Government; included in DPR at S.  No. 8

3.

Development of grounds at Ziekezoue, TM School, Seikhazou and GHS

2008-09

2563.09

Returned to State Government as component ineligible for funding under JNNURM

4.

Solid Waste Management Plan for Greater Kohima

2008-09

3964.86

Returned to State Government due to technical deficiency

5.

Augmentation of Water Supply to Kohima Town

2008-09

21664

Returned to State Government due to technical deficiency

6.

Kohima Town Roads

2008-09

558.72

DPR could not be appraised as one project has already been approved out of the additional allocation and inadequate outlay available

7.

Storm Water Drainage Development Scheme for Kohima (Phase-I)

2008-09

7750

Returned to State Government due to technical deficiency

8.

Integrated Road and Multilevel Parking Project at Kohima

2008-09

7226.79

Approved for Rs. 5042.43 lakhs with ACA commitment of Rs. 4538.19 lakhs.  So far Rs. 1134.55 lakhs has been released as 1st installment for the project.

9.

Construction of Children Park at Kohima

2008-09

397.71

Returned to State Government as DPR not recommended by State Government for sanction from additional allocation

10.

Storm Water Drainage Development Scheme for Kohima (Phase-I)

2009-10

8561.5

Returned to State Government due to technical deficiency

11.

Construction of Road from Kitsubozou Colony to old link road at Kohima

2010-11

280.62

Returned to State Government due to technical deficiency

12.

Kohima Storm Drainage development scheme for Kohima Town

2010-11

4441

Returned to State Government as one project has already been approved out of the additional allocation and inadequate outlay available

13.

Construction of Retaining wall already along with road from NH 6-61 to North Field School, Kohima

 

2010-11

166.48

DPR could not be appraised as one project has already been approved out of the additional allocation and inadequate outlay available

 

 

Annexure-II as referred to in reply to part (a) to (d) of Rajya Sabha Unstarred Question No. 1828 for 25.11.10

 

Rs. In Lakh

Sl No.

Name of the Project

Date of SLSC approval

Date of submission of DPR for technical clearance

Estimates Cost

Appraised cost after technical clearance

ACA involved as per technically appraised cost

Present Status / Remarks

1

2

3

4

5

6

7

8

1.        

Road project at Chumukedima

24-05-07

Feb, 2009

497.00

423.89

381.50

Funds releasedIst instalment of ACA of Rs. 190.75 lakh has been released to the State in September, 2009.

2.        

Road and Drain  project at Mon Town

24-05-07

Feb, 2009

2983.89

2956.00

2660.40

The project cannot be accommodated within the available allocation of Rs. 6.46 crore and State Govt. has not agreed to bear the additional cost involved in the project.

3.        

Water Supply  project at Wokha

24-05-07

Feb, 2009

3284.87

--

--

Technical observations on the project were sent to the State in July, 2009, compliance of the same are still awaited from the State.

4.        

Water Supply  project at Longleng

24-05-07

Feb, 2009

1016.22

1371.98

1234.78

The project cannot be accommodated within the available allocation of Rs. 6.46 crore and State Govt. has not agreed to bear the additional cost involved in the project.

5.        

Water Supply project at  Kiphire

24-05-07

Feb, 2009

700.67

1441.83

1297.65

The project cannot be accommodated within the available allocation of Rs. 6.46 crore and State Govt. has not agreed to bear the additional cost involved in the project.

6.        

Water Supply  project at Peren

24-05-07

Feb, 2009

1264.10

--

--

Technical observations on the project were sent to the State in July, 2009, compliance of the same are still awaited from the State.

7.        

Road  project at Longleng

24-05-07

Not yet

49.00

--

--

DPR is yet to be submitted by the State.

8.        

Road  project at Chiephobozou

24-05-07

Feb, 2009

444.00

408.00

367.20

State Govt. has recently given priority to the project which is under examination.

9.        

Solid Waste  Management  project at Dimapur

08-11-07

June,2010

1127.91

1127.91

--

Technical observations on the project were sent to the State in November, 2010, compliance of the same are still awaited from the State.