Annexure-I as referred to in reply
to part (a) to (d) of Rajya Sabha Unstarred Question No. 1828 for 25.11.2010
(All
figures in Rs. lac)
|
Sl.No. |
Name of
Project |
Year of DPR
submission |
Estimated
cost |
Status |
|
1 |
2 |
3 |
4 |
5 |
|
1. |
Construction of Multi Level Vehicle
Parking at Old Medical Directorate Site |
2008-09 |
2973.45 |
Returned to State Government;
included in DPR at S. No. 8 |
|
2. |
Construction of Multi Level
Vehicle Parking at NST Site |
2008-09 |
1987.08 |
Returned to State Government;
included in DPR at S. No. 8 |
|
3. |
Development of grounds at Ziekezoue, TM School, Seikhazou
and GHS |
2008-09 |
2563.09 |
Returned to State Government as
component ineligible for funding under JNNURM |
|
4. |
Solid Waste Management Plan for
Greater Kohima |
2008-09 |
3964.86 |
Returned to State Government due
to technical deficiency |
|
5. |
Augmentation of Water Supply to |
2008-09 |
21664 |
Returned to State Government due
to technical deficiency |
|
6. |
|
2008-09 |
558.72 |
DPR could not be appraised as one
project has already been approved out of the additional allocation and
inadequate outlay available |
|
7. |
Storm Water Drainage Development
Scheme for Kohima (Phase-I) |
2008-09 |
7750 |
Returned to State Government due
to technical deficiency |
|
8. |
Integrated Road and Multilevel
Parking Project at Kohima |
2008-09 |
7226.79 |
Approved for Rs. 5042.43 lakhs with ACA commitment of Rs. 4538.19 lakhs. So far Rs.
1134.55 lakhs has been released as 1st installment
for the project. |
|
9. |
Construction of |
2008-09 |
397.71 |
Returned to State Government as
DPR not recommended by State Government for sanction from additional
allocation |
|
10. |
Storm Water Drainage Development
Scheme for Kohima (Phase-I) |
2009-10 |
8561.5 |
Returned to State Government due
to technical deficiency |
|
11. |
Construction of Road from Kitsubozou Colony to old link road at Kohima |
2010-11 |
280.62 |
Returned to State Government due
to technical deficiency |
|
12. |
Kohima Storm
Drainage development scheme for |
2010-11 |
4441 |
Returned to State Government as
one project has already been approved out of the additional allocation and
inadequate outlay available |
|
13. |
Construction of Retaining wall
already along with road from NH 6-61 to |
2010-11 |
166.48 |
DPR could not be appraised as one
project has already been approved out of the additional allocation and
inadequate outlay available |
Annexure-II
as referred to in reply to part (a) to (d) of Rajya Sabha Unstarred Question
No. 1828 for 25.11.10
Rs. In
Lakh
|
Sl No. |
Name of
the Project |
Date of
SLSC approval |
Date of
submission of DPR for technical clearance |
Estimates
Cost |
Appraised
cost after technical clearance |
ACA
involved as per technically appraised cost |
Present
Status / Remarks |
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
|
1. |
Road project at Chumukedima |
24-05-07 |
Feb, 2009 |
497.00 |
423.89 |
381.50 |
Funds released—Ist
instalment of ACA of Rs. 190.75 lakh has been
released to the State in September, 2009. |
|
2. |
Road and Drain project at |
24-05-07 |
Feb, 2009 |
2983.89 |
2956.00 |
2660.40 |
The project cannot be
accommodated within the available allocation of Rs. 6.46 crore and State
Govt. has not agreed to bear the additional cost involved in the project. |
|
3. |
Water Supply project at Wokha |
24-05-07 |
Feb, 2009 |
3284.87 |
-- |
-- |
Technical observations
on the project were sent to the State in July, 2009, compliance of the same
are still awaited from the State. |
|
4. |
Water Supply project at Longleng
|
24-05-07 |
Feb, 2009 |
1016.22 |
1371.98 |
1234.78 |
The project cannot be
accommodated within the available allocation of Rs. 6.46 crore and State
Govt. has not agreed to bear the additional cost involved in the project. |
|
5. |
Water Supply project at Kiphire |
24-05-07 |
Feb, 2009 |
700.67 |
1441.83 |
1297.65 |
The project cannot be
accommodated within the available allocation of Rs. 6.46 crore and State
Govt. has not agreed to bear the additional cost involved in the project. |
|
6. |
Water Supply project at Peren |
24-05-07 |
Feb, 2009 |
1264.10 |
-- |
-- |
Technical observations
on the project were sent to the State in July, 2009, compliance of the same
are still awaited from the State. |
|
7. |
Road project at Longleng
|
24-05-07 |
Not yet |
49.00 |
-- |
-- |
DPR is yet to be
submitted by the State. |
|
8. |
Road project at Chiephobozou
|
24-05-07 |
Feb, 2009 |
444.00 |
408.00 |
367.20 |
State Govt. has recently
given priority to the project which is under examination. |
|
9. |
Solid Waste Management
project at Dimapur |
08-11-07 |
June,2010 |
1127.91 |
1127.91 |
-- |
Technical observations
on the project were sent to the State in November, 2010, compliance of the
same are still awaited from the State. |