ANNEX

 

ANNEX REFERRED TO IN REPLY TO PARTS (a) & (b) OF UNSTARRED QUESTION NO.  1603 TO BE ANSWERED IN THE RAJYA SABHA ON 09.08.2010.

******

 

 List of hydro electric projects concurred by CEA in the public and private sector in Arunachal Pradesh as referred to in the reply

 

Sl.

No.

Name of Project

(Capacity)

Implementing Agency

 

Scheduled  commissioning

(Anticipated commissioning)

Status

        CENRAL SECTOR

 

 

1

Subansiri Lower

(8x250= 2000 MW)

 NHPC Limited

2010-11

(2012-13)

Under construction.

2

Kameng

(4x150= 600 MW)

NEEPCO

2009-10

(2013-14)

Under construction.

3

Pare

(2x55 =110 MW)

 

 

NEEPCO

2012-13

(2012-13)

- Civil works awarded to M/s  

  HCC on 31.08.2009.

- Pre-construction activity at 

   site have started.

4

Dibang

(12x250 =

3000 MW)

NHPC Limited

As per TEC,

96 months from date of CCEA’s approval.

- CEA’s concurrence accorded on 23.01.2008

- CCEA approval is yet to be accorded

        PRIVATE SECTOR

 

 

5

Demwe Lower

(5x342+1x40

=1750 MW)

 

Athena Demwe Power Limited

2016-17

(2016-17)

- CEA concurrence on 

   20.11.2009

- Infrastructure works in

   progress

6

Dibbin

(2x60 = 120 MW)

M/s KSK Dibbin Hydro Power Pvt. Ltd.

2014-15

(2014-15)

- CEA concurrence on 

   04.12.2009

- Preliminary works in progress

7

Lower Siang

(9x300 = 2700 MW)

M/s Jaypee Arunachal Power Limited

2016-21

(2016-21)

- CEA concurrence on 

  16.02.2010

- Preliminary works in 

   progress.

 

*******