a) to (c) : The details of
rail projects in Himachal Pradesh with their status and targets wherever fixed
is as under:-
( Rs.
in Cr.)
S.No. |
Name of the project |
Cost |
Present status with time of
completion wherever fixed. |
1. |
Bhanupalli-Bilaspur-Beri
new line (63.1 km.) |
1046.88 |
Final Location Survey (FLS) for the project has
been completed and part detailed estimate for the first 20 km of the project
section (Bhanupalli-Dharot) has
already been sanctioned. Contract for
earthwork and minor bridges for the first 3 km. has been awarded. Land acquisition has been taken up. |
2. |
Chandigarh-Baddi
new line (33.23 km.) |
328.14 |
The work of Chandigarh-Baddi was included in
Budget 2007-08. State Govts. of |
3. |
Nangal
Dam-Talwara new line (83.74 km.) |
730.00 |
Nangal Dam-Churaru Takrala (33 km.) has already
been commissioned. Churaru Takrala-Amb Anduara (11.6 km.) portion has also been completed.
The work will now be taken up in the next phase between Amb Anduara – Kartoli
Punjab. |
(d)&(e) : The work of Nangal Dam-Talwara new line is
being done in phases as per the
availability of resources. The work
remained suspended for a long time
as State Government of Himachal Pradesh
did not provide land free of cost as per the commitment. Due to the long gestation period, the cost
has increased considerably. State
Government of Himachal Pradesh has also been requested to share cost of the
project.
*****