DEPARTMENT OF ATOMIC ENERGY

 

 

NOTE FOR SUPPLEMENTARIES

 

 

INDEX

 

 

Sl. No.

Subject

Page No.

1.       

Bio – data of Shri Raj Mohinder Singh Majitha

 

1-2

2.       

Bio – data of Shri Ram Jethmalani

 

3-4

3.       

Part I – Executive Summary

 

5-6

4.       

Part II – Anticipated Questions & Answers

 

 7-12

5.       

Part III – Detailed Note for Supplementaries

 

 13-18

6.       

Similar questions asked by other members in previous sessions with answer (Rajya Sabha)

 

 19-21

7.       

Similar questions asked by other members in previous sessions with answer (Lok Sabha)

 22

 


 

GOVERNMENT OF INDIA

DEPARTMENT OF ATOMIC ENERGY

 

RAJYA SABHA STARRED QUESTION NO.466 FOR ANSWER ON 06.08.2009 BY S/SHRI RAJ MOHINDER SINGH MAJITHA AND RAM JETHMALANI REGARDING LAND FOR NUCLEAR POWER PROJECT

 

PART I

   EXECUTIVE SUMMARY

The Question

             The thrust of the question is whether the Government has finalized sites for setting up of nuclear power projects in co-operation with American Companies.  The question also seeks to ascertain the estimates of the land required for the projects at each place.  Agricultural land, out of the total land marked for the project is also required to be ascertained. 

 

The international co-operation agreements with France, Russia and USA opened up the possibilities of setting up large capacity of Light Water Reactors (LWR).  These reactors need very large amount of cooling water and therefore coastal sites are preferred for such reactors.  The coastal sites also have advantage of transportation and heavy equipment by sea route.

 

The Government of India has constituted a Site Selection Committee (SSC) in the year 2005 to recommend a panel of coastal sites for setting up a nuclear parks of about six reactors at each site. The SSC  requested the State Governments for identification and recommendations of suitable sites, along the coast, for setting up such power reactors.  In response, the Governments of Andhra Pradesh, Gujarat, Orissa and West Bengal have proposed sites for consideration by the SSC.  The SSC has evaluated potential of these sites and submitted recommendation to the Government.  The draft Cabinet note for in-principle approval of the sites is currently in the process of inter-ministerial consultations.

 

The Government had in the year 2005, approved in-principle sites at Kudankulam and Jaitapur in Maharashtra for setting up 2 x 1000 MWe LWR.  Kudankulam – 1&2 (2 x 1000 MWe) LWRs are already under construction at Kudankulam, Tamil Nadu.  The in-principle approval in the year 2005 was for setting up two additional units (KK-3&4) at Kudankulam.  The site for two units at Jaitapur, Maharashtra was a new site. 

            The site at Kudankulam has potential for setting up additional two units (KK- 5&6).  Similarly, the site at Jaitapur has also additional potential for setting up more reactors.

 

            The proposal under the consideration of the Government seeks in-principle approval for setting up reactors at three sites, namely Andhra Pradesh, Gujarat and West Bengal and utilizing full potential of the sites at Kudankulam and Jaitapur.  The proposal also includes two inland sites for plants in Haryana and Madhya Pradesh.

           

            The sites at Chhaya Mithi Virdi, Gujarat, Kovvada in Andhra Pradesh and Haripur in West Bengal are under the consideration for setting up power reactors in co-operation with US Companies though formal decision in this regard is yet to be taken.

 

            The discussions with the State Governments and the recommendations of the SSC have been on the basis of exclusion zone radius of 1.5 km.  The proposal to reduce the exclusion radius to 1 km based on the current design standards of the contemporary reactors worldwide and consistent with the global practices is under consideration.  Based on the exclusion radius of 1 km the land requirement for six reactors at each site is about 500 hectares.

           

            While it is planned to start work on a set of two reactors in the first instance followed by commencement of work on another set of two reactors after a period of three to five years when the work on first set of reactors will taper off, the land required for all the reactors at a particular site is proposed to be acquired in the first instance itself.  Thus there would be no additional land required for future expansion of the projects. 

           

            The setting up of nuclear power stations at coastal locations requires  foreshore facilities for intake channels etc. and therefore has to be as close to the sea as possible, consistent with Coastal Management Zone (CMZ) regulations.   The land marked at each of the sites is on the basis of exclusion radius of 1.5 km and the agricultural land out of the total land varied from site to site.  With the proposed reduction of exclusion radius from 1.5 km to 1 km, the land requirement has come down by about 40%.  The plot area tentatively based on reduced exclusion radius will need to be relocated within the area already identified at each of the sites in consultation with the State Government so as to minimize the agricultural land.

********


GOVERNMENT OF INDIA

DEPARTMENT OF ATOMIC ENERGY

 

RAJYA SABHA STARRED QUESTION NO.466 FOR ANSWER ON 06.08.2009 BY S/SHRI RAJ MOHINDER SINGH MAJITHA AND RAM JETHMALANI REGARDING LAND FOR NUCLEAR POWER PROJECT

 

PART – II

 ANTICIPATED QUESTIONS & THEIR ANSWERS

 

How many nuclear power plants are planned to be set up based on foreign cooperation?

           

            About 40,000 MWe nuclear power capacity comprising of Light Water Reactors (LWRs) of diverse technologies, each of 1000 MWe and above, are planned to be set up based on foreign cooperation. These are planned to be set up as nuclear power parks, each of about 6000 to 10,000 MWe, consisting of six to eight LWRs at coastal sites. The exact number of reactors to be set up will depend on the capacities of the reactors set up.

 

What are the LWR technologies under consideration?

 

            There are four major state of the art large LWR designs (termed Generation III Plus) under consideration. These are EPRs of AREVA, France, VVERs of Atomstroyexport (ASE), Russian Federation, ABWRs of GE Hitachi Nuclear (GEH), USA and AP1000 of Westinghouse Electric Company (WEC) USA.

 

What is the status of nuclear cooperation with the USA?

 

            Consequent to the conclusion of the intergovernmental agreement (123 Agreement) with the USA in October 2008, MoUs have been signed between Nuclear Power Corporation of India Limited (NPCIL) and two US companies -GE Hitachi Nuclear (GEH) and Westinghouse Electric Company (WEC) in March 2009 & May 2009 respectively for starting discussions on techno-commercial aspects of their respective technologies. Preliminary discussions for finalisation of scope of works, the model of contract, etc. have begun at the company level.


What are the criteria for siting of a nuclear power plant?

           

The guidelines for siting of nuclear power plants in the country are issued by the Atomic Energy Regulatory Board (AERB). Sound foundation conditions, availability of large water body for meeting the cooling water requirements, low population density, magnitude of land acquisition and rehabilitation of the affected population, power evacuation, available infrastructure, land use pattern, distance from sensitive installations, archaeological monuments, large population centres and international borders are some of the considerations for first order evaluation.

 

What is the area required for setting up a nuclear power plant? 

 

The requirement of land for setting up a nuclear power station includes land needed for locating the plant and auxiliary buildings and establishment of an exclusion zone of 1.5 km (at present) around the plant where no habitation is permitted. The establishment of exclusion zone is a regulatory requirement. The total area required for setting up four-unit station at inland site typically is about 1100 Ha, while at a costal locations, it is lesser, at about 750 hectares. The actual area required depends on the surface features of the site like water bodies, hills etc.

 

Why are coastal sites preferred for setting up large size nuclear power plants?

 

            Coastal sites are preferred for setting up large capacity reactors on account of availability of abundant sea water for condenser cooling and ease of transportation of heavy, over dimensional equipment by sea in case of nuclear power reactors set up based on international cooperation. In land sites are considered for small & medium sized reactors.

 

Does India have any experience of setting up large reactors based on international cooperation?

 

Two VVERs of 1000 MWe each are being set up at Kudankulam in Taminadu in technical cooperation with Russian Federation. These are at an advanced stage of construction and are expected to start generation in 2009/2010. India has gained significant experience in setting up these reactors, in terms of adoption of the technology, contract formulation, construction, erection of equipment and their commissioning.  The construction of these units has been taken up by Indian industries/ companies.

 

What will be the source of fuel for the reactors based on international cooperation ? What will be the annual requirement of fuel?

 

The nuclear reactors based on international cooperation  will be Light Water Reactors (LWRs) ,fuelled by low enriched fuel (4-5%). Necessary guarantees for lifetime fuel supplies will be incorporated in the commercial agreements/contracts. The annual requirement of low enriched uranium fuel will be about 35 tons per 1000 MWe capacity.

 

What will the investment cost of reactors based on international cooperation and the tariff of electricity generated from them?

 

The investment cost of setting up such reactors in India will depend on the business model adopted and the extent of indigenization. The costs will be known only after commercial contracts are negotiated. Indigenous nuclear power is competitive with contemporary coal thermal power at locations away from coalmines. In respect of reactors based on international cooperation too, efforts will be made to ensure viable tariff regime.

Are there any proposals to permit private/ foreign participation in nuclear power sector?

 

Currently, Nuclear Power Stations can be set up only by Government or a Government company in accordance with the provisions of the Atomic Energy Act. NPCIL & BHAVINI are the two Government companies authorised to set up nuclear power stations. The private sector participation is possible through a Joint Venture, in which NPCIL is a majority partner. In addition, private sector has major participation in supply of equipment & services.

Involvement of private sector in setting up nuclear power plants would need an amendment of the Atomic Energy Act.  All aspects of setting up such projects will be comprehensively considered by the Government before according them approval.


How are the LWR projects proposed to be funded?

In the XI Plan, work is proposed to be started on 10 imported LWRs. The projects are proposed to be funded by a mix of debt & equity, at a ratio of about 70:30.  The equity requirements of these projects are proposed to be met from the reserves and surpluses of Nuclear Power Corporation of India Limited, while the debt is proposed to be sourced from external credit and market borrowings. For projects beyond the XI Plan, if needed, NPCIL will explore other options of raising equity.

 

How is safety ensured in setting up and operating nuclear power plants? 

            Utmost attention is given to nuclear safety in Indian nuclear power plants. Principle of “SAFETY   FIRST- PRODUCTION LATER” is adopted in all activities. The overriding importance to safety encompasses the entire gamut of activities associated with nuclear power plants (NPPs), that is, siting, design, construction, commissioning, and operation. In all these activities, a major effort is devoted to ensuring safety of operating personnel, public as well as the environment.

            A systematic approach using well-defined principles is followed in the design of the nuclear power plants to provide the required safety features adopting principles of defence-in-depth, diversity and redundancy. Nuclear Power Plants are constructed in accordance with the design intent, and with required quality of workmanship to very strict quality standards. The manufacture of components and equipment as well as the erection, testing and commissioning activities are performed under stringent Quality Assurance Programmes. The operations are performed using well laid out procedures by thoroughly well qualified and trained staff. The operators are trained using simulators and periodically re-trained for sharpening their reflexes and skills.

The specific safety features of the Indian Nuclear Power Reactors are:

a)         In design of nuclear power plants, safety principles of redundancy, diversity and fail-safe design features are followed. Physical separation between redundant safety systems and diversity of equipment of critical safety systems ensure that common mode failures due to fire etc. do not occur.

b)         The defence-in-depth approach in design ensures that there are multiple barriers (fuel matrix, fuel clad, primary pressure pipe, primary containment and secondary containment) to be crossed before radioactivity can escape to environment.

c)         There is a multi-tier system of review by the Atomic Energy Regulatory Board (AERB) during all the stages.

d)         For nuclear power plant operation, operating personnel for specific positions are licensed by AERB and then only allowed to perform the task.

e)         An exclusion zone of 1.6 km radius around the reactors is established where the land is acquired and fenced.  No resident public habitation is permitted. In addition a sterilised zone of 5 km. radius surrounds the plant where only normal growth of existing population is allowed.

f)          Emergency preparedness, as a matter of abundant caution, is ensured by well laid down plans and procedures and regular rehearsals by the plant and state authorities.

How is the environment around the nuclear power plant monitored to ensure that radioactivity is within permissible limits?

            Each atomic power plant has an Environmental Survey Laboratory (ESL) which is independent of the atomic power plant/ Nuclear Power Corporation of India Limited (NPCIL) management and reports directly to Bhabha Atomic Research Centre (BARC). These Laboratories are set up before pant construction so as to generate base line data. ESLs undertake continuous surveillance of the environment by analysing the environmental matrices like air, water and foodstuff like cereals, milk, vegetables, fish etc, for their radioactivity contents. The radiation dose to the members of the public is computed from these measurements and is found to be only a fraction of the permissible dose limits prescribed by Atomic Energy Regulatory Board (AERB).

            Epidemiological surveys have been conducted at all operating nuclear power plants by Tata Memorial Centre with active participation of local medical colleges.  These surveys have concluded that there is no radiation induced effect on the health of people around the plant due to operation of nuclear power plants.

*********

 

 

 

GOVERNMENT OF INDIA

DEPARTMENT OF ATOMIC ENERGY

 

RAJYA SABHA STARRED QUESTION NO.466 FOR ANSWER ON 06.08.2009 BY S/SHRI RAJ MOHINDER SINGH MAJITHA AND RAM JETHMALANI REGARDING LAND FOR NUCLEAR POWER PROJECT

 

 

PART III  

 

 SUPPLEMENTARY INFORMATION

The following figure shows the present locations of nuclear power plants in India:

 


Nuclear Power Stations in Operation

The present total nuclear power capacity in the country is 4120 MWe with 17 reactors. The details of nuclear power stations in operation are given in the Table below:

Unit-Location

Reactor Type

Capacity (MWe)

Date of Commercial Operation

TAPS-1 Tarapur, Maharashtra

BWR

160

28-Oct-1969

TAPS-2 Tarapur, Maharashtra

BWR

160

28-Oct-1969

RAPS-1 Rawatbhata, Rajasthan *

PHWR

100

16-Dec-1973

RAPS-2 Rawatbhata, Rajasthan

PHWR

200

01-Apr-1981

MAPS-1 Kalpakkam, Tamilnadu

PHWR

220

27-Jan-1984

MAPS-2 Kalpakkam, Tamilnadu

PHWR

220

21-Mar-1986

NAPS-1 Narora, Uttar Pradesh

PHWR

220

01-Jan-1991

NAPS-2 Narora, Uttar Pradesh

PHWR

220

01-Jul-1992

KAPS-1 Kakrapar, Gujarat

PHWR

220

06-May-1993

KAPS-2 Kakrapar, Gujarat

PHWR

220

01-Sep-1995

KAIGA-2, Kaiga, Karnataka

PHWR

220

16-Mar-2000

RAPS-3 Rawatbhata, Rajasthan

PHWR

220

01-Jun-2000

KAIGA-1Kaiga, Karnataka

PHWR

220

16-Nov-2000

RAPS-4 Rawatbhata, Rajasthan

PHWR

220

23-Dec-2000

TAPS-4 Tarapur, Maharashtra

PHWR

540

12-Sep-2005

TAPS-3 Tarapur, Maharashtra

PHWR

540

18-Aug-2006

KAIGA-3 Kaiga, Karnataka

PHWR

220

06-May-2007

Total

 

4120

 

 

BWR: Boiling Water Reactor (LWR)   PHWR: Pressurised Heavy Water Reactor

      * Owned by DAE and operated by NPCIL

 

Reactors under Construction

 

There are six reactors under construction; three of them are PHWRs of 220 MWe, two LWRs of 1000 MWe introduced as an additionality being executed in technical cooperation with Russian Federation and a second stage Fast Breeder Reactor (PFBR) of 500 MWe. The details of the projects under construction are shown below:


 


Scheme

Location

Capacity

(MWe)

Expected date of

Completion

Kaiga Atomic Power Project

Unit 4

Kaiga, Karnataka

220

PHWR

2010

Kudankulam Nuclear Power Project

Units -1&2

Kudankulam,

Tamilnadu

2X1000 MWe LWRs

 

2010

Rajasthan Atomic Power Project

Units-5&6

Rawatbhata,

Rajasthan

2X220

PHWRs

2009

Prototype Fast Breeder Reactor (PFBR)

Kalpakkam, Tamilnadu

 

1X500 (FBR)

2011

 

            The work on RAPP 5&6 & Kaiga 4 PHWRs is completed and awaiting fuel supply.

 

Capacity Buildup

 

With the progressive completion of the projects under construction, the installed nuclear power capacity will reach 7280 MWe by 2011.

 

Future Plans

 

            The Integrated Energy Policy of the country envisages reaching a nuclear power capacity of 63,000 MWe by the year 2032. Large-scale expansion of the nuclear power, based both on indigenous reactors and reactors based on international cooperation, is planned.   

 


International Cooperation Initiatives & Setting up of LWRs

 

            The Government had taken initiatives on international cooperation in nuclear energy. The fruition of those efforts have led to ending of India’s international isolation and facilitated nuclear commerce. A chronology of the events is given below:

 

S.No.

Date

Event

Place

1

Jul 18, 2005

Joint Statement by India & USA on enabling full civil nuclear energy cooperation

Washington DC, USA

2

Feb 27, 2006

Suomoto statement by the PM in Parliament on civil nuclear cooperation with USA

New Delhi, India

3

Mar 02, 2006

Agreement between India and USA on Separation Plan (suo moto statement by PM on Mar 07, 2006)

New Delhi, India

4

Dec 18, 2006

US Legislation on Nuclear Cooperation with India signed by the US President

Washington DC, USA

5

Aug 03, 2007

Text of 123 Agreement released

USA & India

6

July 09, 2008

Draft text of India specific Safeguards Agreement circulated to IAEA Board

IAEA, Vienna

7

Aug 01, 2008

IAEA Board adopts India specific Safeguards Agreement

IAEA, Vienna

8

Sep 06, 2008

NSG grants waiver to India

IAEA, Vienna

9

Sep 30, 2008

India & France sign agreement on civil nuclear cooperation

Paris, France

10

Oct 10, 2008

123 Agreement signed between India & USA

Washington DC, USA

11

Dec 06, 2008

India & Russia sign agreement on civil nuclear cooperation

New Delhi, India

12

Dec 17, 2008

Agreement signed between DAE and AREVA for supply of 300 tons of fuel

 

13

Jan 24, 2009

NPCIL & KAZATOMPROM sign MoU for cooperation in nuclear industry

New Delhi, India

14

Feb 04, 2009

NPCIL & AREVA sign agreement for setting up EPRs at Jaitapur in Maharashtra

New Delhi, India

15

Feb 11, 2009

Agreement to be signed between DAE & Russian firm   for supply of 2000 tons of fuel pellets

Mumbai, India

16

Feb 14, 2009

NPCIL & NTPC sign MoU to incorporate a Joint Venture for setting nuclear power plants

Mumbai, India

17

Mar 23, 2009

NPCIL & GEH, USA sign an MoU for setting up ABWRs in India

Mumbai, India

18

May 28, 2009

NPCIL & WEC, USA sign MoU for setting up AP1000 reactors in India

Mumbai, India

 

 

 

 


US LWR technologies

           

            There state of the art large LWR designs (termed Generation III Plus) of the USA are 1350 MWe ABWRs of GE Hitachi Nuclear (GEH), USA and 1100 MWe AP1000 of Westinghouse Electric Company (WEC) USA. Four ABWRs are in operation in Japan and three are under construction, one in Japan and two in Taiwan. Four AP 1000 reactors are under construction in China. AP1000 units are also planned in the USA. In the first instance, reactors in cooperation with each of the companies are planned to be set up to have technological diversity.

 

Nuclear Power Parks

The nuclear power plants based on international co-operation are planned to be set up as nuclear power parks, each of about 8000 to 10,000 MWe, consisting of six to eight LWRs. The work is planned to be taken up on set of two reactors in the first instance, followed by another set at the same site when the work on first set of reactors begins to taper off. The land for all the reactors planned at the site is acquired in the beginning, and therefore there is no land acquisition involved for expansion at a later stage.

Land Requirements for Nuclear Power Parks

            Land is required for setting up the plant buildings and for establishing an exclusion zone, (presently 1.5 km) around the reactors where no habitation is permitted, in line with the regulatory requirements. The following sketch shows a typical profile of the land to be acquired for a six unit station at a coastal site:

           

It can be seen that the area required is primarily dictated by the extent of the exclusion zone. The proposal to reduce the exclusion zone radius to 1 km based on the current design standards of the contemporary reactors worldwide and consistent with the global practices is under consideration. This would reduce the land requirement substantially, depending on the number of reactors to be set up at the site.

 

As also can be seen from the figure, the exact land requirement would depend on the profile of the coastline and surface features in the exclusion area (water bodies, hills etc.). An approximate estimate of the land requirement in square km with exclusion zone radius ‘r’ of 1.6 km, 1.5 km and 1km are indicated in the table:

No of Reactors

Land Requirement (sq. km)

r =1.6 km

r = 1.5 km

r = 1.0 km

4

7.510

6.830

3.920

6

8.782

8.043

4.825

8

10.042

9.243

5.725

10

11.290

10.430

6.720

 

******