GOVERNMENT OF INDIA

DEPARTMENT OF ATOMIC ENERGY

 

STATEMENT REFERRED TO IN REPLY TO RAJYA SABHA STARRED QUESTION NO.11 FOR ANSWER ON 02.07.2009 BY S/SHRI D. RAJA AND M.P. ACHUTHAN REGARDING CONSTRUCTION OF NUCLEAR REACTORS

 

 

(a) & (b)    Yes, Sir. Discussions have been held with the agencies of Russian Federation, USA and France for building nuclear reactors with their assistance.  The discussions covered preliminary aspects of technical, organisational, commercial and other issues involved and no specific decisions have been taken.     

 

********


 

 

DEPARTMENT OF ATOMIC ENERGY

 

 

 

NOTE FOR SUPPLEMENTARIES

 

 

 

 

INDEX

 

 

S. No.

Particulars

Page No.

1.

Bio-data of  Shri D. Raja

1-2

2.

Bio-data of  Shri M.P. Achuthan

3

3.

Part I - Executive Summary

4-6

4.

Part-II - Anticipated Questions and Answers

7-11

5.

Part-III - Detailed Note for Supplementaries

12-18

6.

Similar question asked by Shri D. Raja

19-21

7.

Similar questions asked by other members in previous sessions with answers (Rajya Sabha)

22-27

8.

Similar questions asked by other members in previous sessions with answers (Lok Sabha)

28-32

 


GOVERNMENT OF INDIA

DEPARTMENT OF ATOMIC ENERGY

 

RAJYA SABHA STARRED QUESTION NO.11 FOR ANSWER ON 02.07.2009 BY S/SHRI D. RAJA & M.P. ACHUTHAN REGARDING CONSTRUCTION OF NUCLEAR REACTORS .

 

 

PART – I

 

EXECUTIVE SUMMARY

 

The thrust of the question is to know if negotiations were held with foreign countries for building nuclear reactors in the country with their assistance, to move forward with the Indo-US nuclear deal.  

 

Consequent to the conclusion of the international agreements – safeguards agreement with the IAEA and clearance of the Nuclear Suppliers Group, inter governmental agreements have been concluded by India with France, USA and the Russian federation.  Preliminary discussions on technical aspects for setting up nuclear reactors with organizations dealing in nuclear commerce, from these countries have been initiated.

 

With a view to set up large nuclear power capacity in India with foreign cooperation and exploit full potential of such co-operation, about 40,000 MWe of Light Water Reactors (LWRs) is  planned as an additionality to the indigenous nuclear power programme,

 

There are four major state of the art large LWR designs (termed Generation III Plus) which have several advanced safety features. These are EPRs of AREVA, France, VVERs of Atomstroyexport (ASE), Russian Federation, ABWRs of GE Hitachi Nuclear (GEH), USA and AP1000 of Westinghouse Electric Company (WEC) USA. These four global companies are currently setting up or have plans to set up nuclear reactors in Finland, France, Russia, China and the USA.

The technology of each of these four companies is current & contemporary and relative technological evaluation is only in terms of fine technical details. It is considered desirable, in the first instance, to set up reactors in cooperation with each of the companies to have technological diversity, 

 

The nuclear power plants based on international co-operation are planned to be set up as nuclear power parks, each of about 8000 to 10,000 MWe, consisting of six to eight LWRs. The work is planned to be taken up on a set of two reactors in the first instance, followed by another set at the same site when the work on first set of reactors begins to taper off.

 

After the signing of inter-governmental agreements with the respective countries, these companies approached Nuclear Power Corporation of India (NPCIL) for co-operation in setting up nuclear reactors in India. As a first step, MoUs have been signed with them as detailed below:

·        MoU between NPCIL & AREVA on February 4, 2009 for engagement of the two companies for preparing the contract and related details of setting up two to six EPR reactors units

·        MoU between NPCIL & GE Hitachi Nuclear Energy (GEH) on March 20, 2009 for starting discussions on techno-commercial aspects of ABWRs in India

·        MoU between NPCIL & Westinghouse Electric Company (WEC) on May 28, 2009 for starting discussions on techno-commercial aspects of AP 1000 reactors in India.

 

            Preliminary discussions pursuant to these MoUs have just begun. Similar discussions are also in progress with ASE of Russian Federation for setting up additional VVER units in India. These discussions are planned to cover a range of technical and regulatory aspects followed by commercial aspects. The endeavour will be to work out an execution model which will result in viable tariff of electricity from these plants. 

           

            In addition to discussions with NPCIL, these companies have also held discussions with Indian industries for development of component suppliers in the country. This would help enhanced indigenization and is also expected to reduce the capital cost of these LWRs. MoUs have been signed in this regard with Indian companies like Larsen & Toubro by these companies. Discussions for nuclear commerce are also taking place between several foreign companies and Indian industries both at company level and through their respective atomic industry fora.

 

            As stated above, the preliminary discussions have just begun and will take a while for the details to emerge.

 

*********

 


 PART - II

 

 ANTICIPATED QUESTIONS AND THEIR ANSWERS

 

Why are LWRs based on foreign cooperation needed?

 

      LWRs based on foreign cooperation are being introduced as an additionality to the indigenous three-stage programme to achieve rapid augmentation in nuclear capacity. The sequential execution of the three-stage programme, in view of the fuel cycle linkages, needs time to exploit its full potential. In the intervening period, the access to international cooperation and introduction of imported LWRs would enable increasing the nuclear power capacity at a fast pace to meet the growing electricity demand.

 

How much electricity will be generated through these LWRs ?

 

            The LWRs planned are each of capacity 1000 MWe and above. VVERs are of 1000/1250 MWe, EPRs of 1650 MWe,  ABWRs of 1350 MWe and AP 1000 of 1100 MWe capacity. Each reactor of 1000 MWe will generate about 7 billion units (BU) of electricity annually (at average capacity factor of 80%). Thus when about 40,000 MWe capacity LWRs are installed, they will generate about 280 BUs.

 

Does India have any experience of setting up large reactors based on international cooperation?

 

Two VVERs of 1000 MWe each are being set up at Kudankulam in Tamilnadu in technical cooperation with Russian Federation. These are at an advanced stage of construction and are expected to start generation in 2009/2010. India has gained significant experience in setting up these reactors, in terms of adoption of the technology, contract formulation, construction, erection of equipment and their commissioning.  The construction of these units has been taken up by Indian industries/ companies.

What will be the source of fuel for the reactors based on international co-operation? What will be the annual requirement of fuel?

 

The nuclear reactors based on international cooperation  will be Light Water Reactors (LWRs), fuelled by low enriched fuel (4-5%). Necessary guarantees for lifetime fuel supplies will be incorporated in the commercial agreements/contracts. The annual requirement of low enriched enriched uranium fuel will be about 35 tons per 1000 MWe capacity.

 

What is the investment cost of reactors based on international cooperation and the tariff of electricity generated from them?

 

The investment cost of setting up such reactors in India will depend on the business model adopted and the extent of indigenization. The costs will be known only after commercial contracts are negotiated. Indigenous nuclear power is competitive with contemporary coal thermal power at locations away from coalmines. In respect of reactors based on international cooperation too, efforts will be made to ensure viable tariff regime.

 

What are the current nuclear power tariffs?

           

            The current nuclear power tariffs range from 94 Paise/kWh to 292 Paise/kWh with the average tariff being 234 Paise/kWh in 2008-09.

 

What are the proposed locations in the country for setting up of nuclear power plants based on international cooperation? 

                       

            Large capacity Light Water Reactors (LWRs) are planned to be set up with foreign co-operation to enable faster nuclear capacity addition. Coastal sites are preferred for setting up reactors based on international cooperation on account of availability of abundant seawater for cooling and ease in transport and handling of heavy large sized equipment. The Government has accorded ‘in principle’ approval for setting up additional units at Kudankulam, Tamilnadu and a new site at Jaitapur, Maharashtra. The Site Selection Committee (SSC) constituted by the Government in 2005 evaluated coastal sites for location of atomic parks consisting of large capacity reactors based on international cooperation and inland sites for setting up indigenous reactors and submitted its report to the Government. The same is under consideration of the Government.

 

Are there any proposals to permit private/ foreign participation in nuclear power sector?

 

Currently, Nuclear Power Stations can be set up only by Government or a Government company in accordance with the provisions of the Atomic Energy Act. Nuclear Power Corporation of India Limited (NPCIL) & Bharatiya Nabhikiya Vidyut Nigam Limited (BHAVINI) are the two Government companies authorised to set up nuclear power stations. Private sector participation is possible through a Joint Venture, in which NPCIL is a majority partner. In addition, private sector has major participation in supply of equipment & services.

 

Involvement of private sector in setting up nuclear power plants would need an amendment of the Atomic Energy Act.  

 

How are the LWR projects proposed to be funded?

 

In the XI Plan, work is proposed to be started on 10 imported LWRs. The projects are proposed to be funded by a mix of debt & equity, at a ratio of about 70:30.  The equity requirements of these projects are proposed to be met from the reserves and surpluses of Nuclear Power Corporation of India Limited, while the debt is proposed to be sourced from external credit and market borrowings. For projects beyond the XI Plan, if needed, NPCIL will explore other options of raising equity.

 

How is safety ensured in setting up and operating nuclear power plants? 

           

            Utmost attention is given to nuclear safety in Indian nuclear power plants. Principle of “SAFETY   FIRST- PRODUCTION LATER” is adopted in all activities. The overriding importance to safety encompasses the entire gamut of activities associated with nuclear power plants (NPPs), that is, siting, design, construction, commissioning, and operation. In all these activities, a major effort is devoted to ensuring safety of operating personnel, public as well as the environment.

 

            A systematic approach using well-defined principles is followed in the design of the nuclear power plants to provide the required safety features adopting principles of defence-in-depth, diversity and redundancy. Nuclear Power Plants are constructed in accordance with the design intent, and with required quality of workmanship to very strict quality standards. The manufacture of components and equipment as well as the erection, testing and commissioning activities are performed under stringent Quality Assurance Programmes. The operations are performed using well laid out procedures by thoroughly well qualified and trained staff. The operators are trained using simulators and periodically re-trained for sharpening their reflexes and skills.

           

The specific safety features of the Indian Nuclear Power Reactors are:

a)         In design of nuclear power plants, safety principles of redundancy, diversity and fail-safe design features are followed. Physical separation between redundant safety systems and diversity of equipment of critical safety systems ensure that common mode failures due to fire etc. do not occur.

b)         The defence-in-depth approach in design ensures that there are multiple barriers (fuel matrix, fuel clad, primary pressure pipe, primary containment and secondary containment) to be crossed before radioactivity can escape to environment.

c)         There is a multi-tier system of review by the Atomic Energy Regulatory Board (AERB) during all the stages.

d)         For nuclear power plant operation, operating personnel for specific positions are licensed by AERB and then only allowed to perform the task.

e)         An exclusion zone of 1.6 km radius around the reactors is established where the land is acquired and fenced.  No resident public habitation is permitted. In addition a sterilised zone of 5 km. radius surrounds the plant where only normal growth of existing population is allowed.

f)          Emergency preparedness, as a matter of abundant caution, is ensured by well laid down plans and procedures and regular rehearsals by the plant and state authorities.

 

How is the environment around the nuclear power plant monitored to ensure that radioactivity is within permissible limits?

           

            Each atomic power plant has an Environmental Survey Laboratory (ESL) which is independent of the atomic power plant/ Nuclear Power Corporation of India Limited (NPCIL) management and reports directly to Bhabha Atomic Research Centre (BARC). These Laboratories undertake continuous surveillance of the environment by analysing the environmental matrices like air, water and foodstuff like cereals, milk, vegetables, fish etc, for their radioactivity contents. The radiation dose to the members of the public is computed from these measurements and is found to be only a fraction of the permissible dose limits prescribed by Atomic Energy Regulatory Board (AERB).

*******

 PART – III

 

SUPPLEMENTARY INFORMATION

 

The Indigenous Three Stage Programme

 

            The three-stage nuclear power programme has been formulated in the context of our limited uranium but abundant thorium reserves. The three-stage programme has important fuel cycle linkages and has to be gone through sequentially.

 

The following graphic shows the power potential and status of the three-stage programme.

            The sequential execution of the three-stage programme, in view of the fuel cycle linkages, needs time.

 


Additionalities

 

            Additionalities to the indigenous programme have been introduced to add large nuclear power capacity in the near term, to meet the growing electricity demand. Two LWRs of 1000 MWe are under construction at Kudankulam, Tamilnadu.

 

Nuclear Power Stations in Operation

 

The present total nuclear power capacity in the country is 4120 MWe with 17 reactors. The details of nuclear power stations in operation are given in the Table below:

Unit-Location

Reactor Type

Capacity (MWe)

Date of Commercial Operation

FUELLED BY LOW ENRICHED IMPORTED URANIUM.

TAPS-1 Tarapur, Maharashtra

BWR

160

28-Oct-1969

TAPS-2 Tarapur, Maharashtra

BWR

160

28-Oct-1969

FUELLED BY INDIGENOUS NATURAL URANIUM

RAPS-1 Rawatbhata, Rajasthan *

PHWR

100

16-Dec-1973

RAPS-2 Rawatbhata, Rajasthan

PHWR

200

01-Apr-1981

MAPS-1 Kalpakkam, Tamilnadu

PHWR

220

27-Jan-1984

MAPS-2 Kalpakkam, Tamilnadu

PHWR

220

21-Mar-1986

NAPS-1 Narora, Uttar Pradesh

PHWR

220

01-Jan-1991

NAPS-2 Narora, Uttar Pradesh

PHWR

220

01-Jul-1992

KAPS-1 Kakrapar, Gujarat

PHWR

220

06-May-1993

KAPS-2 Kakrapar, Gujarat

PHWR

220

01-Sep-1995

KAIGA-2, Kaiga, Karnataka

PHWR

220

16-Mar-2000

RAPS-3 Rawatbhata, Rajasthan

PHWR

220

01-Jun-2000

KAIGA-1Kaiga, Karnataka

PHWR

220

16-Nov-2000

RAPS-4 Rawatbhata, Rajasthan

PHWR

220

23-Dec-2000

TAPS-4 Tarapur, Maharashtra

PHWR

540

12-Sep-2005

TAPS-3 Tarapur, Maharashtra

PHWR

540

18-Aug-2006

KAIGA-3 Kaiga, Karnataka

PHWR

220

06-May-2007

Total

4120

 

BWR: Boiling Water Reactor  (LWR)        PHWR: Pressurised Heavy Water Reactor

      * Owned by DAE and operated by NPCIL

 
Reactors under Construction

 

There are six reactors under construction, three of them are PHWRs of 220 MWe, two LWRs of 1000 MWe introduced as an additionality and a second stage Fast Breeder Reactors (PFBR) of 500 MWe. The details of the projects under construction are shown below:

Scheme

Location

Capacity

(MWe)

Expected date of

Completion

 

Kaiga Atomic Power Project

Unit 4

Kaiga, Karnataka

220

PHWR

2010

 

Kudankulam Nuclear Power Project

Units -1&2

Kudankulam,

Tamilnadu

2X1000 MWe LWRs

 

2010

 

Rajasthan Atomic Power Project

Units-5&6

Rawatbhata,

Rajasthan

2X220

PHWRs

2009

 

Prototype Fast Breeder Reactor (PFBR)

Kalpakkam, Tamilnadu

 

1X500 (FBR)

2011

 

            The work on RAPP 5&6 & Kaiga 4 PHWRs is completed and awaiting fuel supply.     On completion of these projects progressively during the current five year plan, the nuclear installed capacity will reach 7280 MWe

 

Nuclear Power Programme- Future Plans

 

            The Integrated Energy Policy of the country envisages reaching a nuclear power capacity of 63,000 MWe by the year 2032. Large-scale expansion of the nuclear power, based both on indigenous reactors and  reactors based on international cooperation, is planned.

 

The XI Plan proposals envisage starting work on 8 Pressurised Heavy Water Reactors of 700 MWe each, four Fast Breeder Reactors of 500 MWe each and one Advanced Heavy Water Reactor of 300 MWe. 

            It is planned to start work on an additional 10,000 MWe capacity based on international cooperation, as additionality to the indigenous programme in the XI Plan.

 

International Cooperation Initiatives & Setting up of LWRs

           

            The Government had taken initiatives on international cooperation in nuclear energy. The fruition of those efforts have led to ending of India’s international isolation and facilitated nuclear commerce. A chronology of the events is given below:

S.No.

Date

Event

Place

1

Jul 18, 2005

Joint Statement by India & USA on enabling full civil nuclear energy cooperation

Washington DC, USA

2

Feb 27, 2006

Suomoto statement by the PM in Parliament on civil nuclear cooperation with USA

New Delhi, India

3

Mar 02, 2006

Agreement between India and USA on Separation Plan (suo moto statement by PM on Mar 07, 2006)

New Delhi, India

4

Dec 18, 2006

US Legislation on Nuclear Cooperation with India signed by the US President

Washington DC, USA

5

Aug 03, 2007

Text of 123 Agreement released

USA & India

6

July 09, 2008

Draft text of India specific Safeguards Agreement circulated to IAEA Board

IAEA, Vienna

7

Aug 01, 2008

IAEA Board adopts India specific Safeguards Agreement

IAEA, Vienna

8

Sep 06, 2008

NSG grants waiver to India

IAEA, Vienna

9

Sep 30, 2008

India & France sign agreement on civil nuclear cooperation

Paris, France

10

Oct 10, 2008

123 Agreement signed between India & USA

Washington DC, USA

11

Dec 06, 2008

India & Russia sign agreement on civil nuclear cooperation

New Delhi, India

12

Dec 17, 2008

Agreement signed between DAE and AREVA for supply of 300 tons of fuel

 

13

Jan 24, 2009

India & Kazakhstan sign agreement on nuclear cooperation

New Delhi, India

14

Jan 24, 2009

NPCIL & KAZATOMPROM sign MoU for cooperation in nuclear industry

New Delhi, India

15

Feb 04, 2009

NPCIL & AREVA sign agreement for setting up EPRs at Jaitapur in Maharashtra

New Delhi, India

16

Feb 11, 2009

Agreement to be signed between DAE & Russian firm   for supply of 2000 tons of fuel pellets

Mumbai, India

17

Feb 14, 2009

NPCIL & NTPC sign MoU to incorporate a Joint Venture for setting nuclear power plants

Mumbai, India

18

Mar 23, 2009

NPCIL & GEH, USA sign an MoU for setting up ABWRs in India

Mumbai, India

19

May 28, 2009

NPCIL & WEC, USA sign MoU for setting up AP1000 reactors in India

Mumbai, India

 

 

Setting up of large capacity LWRs

 

With a view to set up large nuclear power capacity in India with international cooperation and exploit full potential of such co-operation for the country, as an additionality to the indigenous nuclear power programme, about 40,000 MWe of Light Water Reactors (LWRs) is planned.

 

There are four major state of the art large LWR designs (termed Generation III Plus) which have several advanced safety features. These are EPRs of AREVA, France, VVERs of Atomstroyexport (ASE) of Russian Federation, ABWRs of GE Hitachi Nuclear (GEH), USA and AP1000 of Westinghouse Electric Company (WEC) USA. In the first instance, reactors in cooperation with each of the companies are planned to be set up to have technological diversity. The perspectives of the reactors planned are shown below:


VVER 392 – Capacity 1000 MWe by ASE, Russian Federation

EPR – Capacity 1650 MWe by AREVA, France

 

ABWR  Capacity 1350 MWe by GEH, USA

 

 

 

AP1000 – Capacity 1100 MWe

 

 

 

 

 

 

 

 

 

 

 

 

Current Status on the discussions

 

            The enabling frameworks have been put in place with the conclusion of inter-governmental agreements. At the governmental level, no negotiations have been held.  With a view to come to the negotiation stage, at the governmental level, preliminary discussions including MoUs for finalisation of scope of works the model of contract, etc. have begun at the company level.

 

*********