GOVERNMENT OF INDIA MINISTRY OF RAILWAYS

RAJYA SABHA STARRED QUESTION NO. 103

TO BE ANSWERED ON 10.07.2009

 

 

STATUS OF RAIL PROJECTS IN ANDHRA PRADESH

 

 

* 103.   SHRI NANDI YELLA1 AH:

 

Will the Minister of RAILWAYS be pleased to state:

(a)   the details of completed/ongoing rail line works in Andhra Pradesh during the last two years, indicating total number of over/under bridges and manned/unmanned crossings built therewith;

(b)   whether all these works were executed/are progressing as per schedule; and

(c)   if not, the reasons therefor, project-wise, separately?

 

ANSWER

MINISTER OF RAILWAYS

(KUMARI MAMATA BANERJEE)

 

(a)    to (c): A Statement is laid on the Table of the Sabha.

 

STATEMENT REFERRED TO IN REPLY TO PART (a) TO (c) OF STARRED QUESTION NO. 103 BY SHRI NANDI YELLAIAH TO BE ANSWERED ON 10.07.2009 IN RAJYA SABHA REGARDING STATUS OF RAIL PROJECTS IN ANDHRA PRADESH.

 

 

(a) : The details of ongoing rail line works in Andhra Pradesh including the sections completed during the last two years and total number of over/under bridges and manned/unmanned level crossings built therewith are as under:-

 

S.No.

Plan Head

Name of the Project

Sections completed in last 2 years

1.

New Line

Cuddapah-Bangalore

2.

New Line

Attipattu-Puttur

3.

New Line

Rayadurg-Tumkur

4.

New Line

Jaggayyapeta-Mellacheruvu

5..

New Line

Peddapalli-Karimnagar-Nizamabad

Karimnagar-Jagityal

6..

New Line

Gadwal-Raichur

7.

New Line

Macherla-Nalgonda

8.

New Line

Kakinada-Pithapuram

9.

New Line

Nandyal-Yerraguntla

Yerraguntla-Nossam

10.

New Line

Munirabad-Mahabubnagar

11.

New Line

Obulavaripalle-Krishnapatnam

 

12.

New Line

Kotipalli-Narsapur

13.

New Line

Vishnupuram-Janpahad

14.

New Line

Tindivanum-Nagari

15.

New Line

Manoharabad-Kotapalli

16.

Gauge Conversion

Dharmavaram-Pakala

Pakala-Madanapalle

17.

Gauge Conversion

Guntur-Guntakal-Kalluru

Guntakal-Kalluru

18.

Gauge Conversion

Naupada-Gunupur

Naupada-Parlakimidi

 

19.

Doubling

Gooty-Renigunta

Pullampet-Bhakrapeta

20.

Doubling

Raichur-Guntakal

21

Doubling

Raghavapuram-Mandamarri (Patch tripling)

22.

Doubling

Vizianagaram-Kottavalasa 3rd line

23.

Doubling

Kottavalasa-Simhanchalam North-4th line

24.

Doubling

Samalkot-Kakinada

Samalkot-Kakinada

25.

Doubling

Guntur-Krishna Canal.

Guntur-Krishna Canal

11 RUBs, 2 ROBs, 68 Manned and 79 Unmanned level crossings have been provided in the completed new line, gauge conversion and doubling sections.

(b): Railways have a huge throw forward of ongoing projects, under new lines, gauge conversion, doublings, railway electrification and metropolitan transport projects. Due to limited availability of resources, the projects take long time in completion. The targets for the projects are generally fixed on yearly basis based on the availability of resources and progress made in the project and therefore, many of the projects get completed in phases. No time frame for completion of all the projects is feasible to be fixed in such a scenario The main reasons for delay have been paucity of funds, delay in land acquisition and environmental/forestry clearance, failure of contracts, adverse law and order conditions and other market forces affecting the progress.

 

 

(c): The details of projects where targets had been fixed but had been delayed are as under:-

 

Name of the Project

Targets fixed earlier/ revised

Remarks & reasons for delay

Jaggayapeta-Mallacheruvu New Line (19.1 km.)

2007-08/ 2009-10

Delay due to change of alignment as per suggestion of beneficiaries and delay in land acquisition.

Dharmavaram-Pakala Gauge Conversion (227 km.)

2008-09/ 2009-10

Pakala-Madanapalle (82 km.) completed. Delay due to slow progress of works and delay in availability of PSC sleepers.